How will the utility companies temporarily relocate during construction and what is their timeline for relocating their utilities?

Question: How will the utility companies temporarily relocate during construction and what is their timeline for relocating their utilities?

Response: Centerpoint Energy will cut and cap their gas main at the limits of the bridge prior to bridge demolition. Xcel Energy and Centurylink are on the overhead lines and will temporarily relocate to a utility pole that will be placed on private property on the NE side of the bridge and this relocation work is planned to be complete prior to bridge demolition as well.