PROJECT QUESTION: After splicing in the 6 strand pigtail are the balance of the 144 strands of fiber to be spliced to each other in the pull vault located at CSAH 101 and Hanus Rd? Reference drawing 450.

Question:
After splicing in the 6 strand pigtail are the balance of the 144 strands of fiber to be spliced to each other in the pull vault located at CSAH 101 and Hanus Rd? Reference drawing 450.

Response:
Please refer to Division SS-5.9, the interconnect pay item includes providing and installing the 144 SM fiber optic cable. Although it does not specifically state that the remaining strands are to be spliced to each other section SS-5.9 does refer to all cable termination, connectors, mechanical splices, etc. needed to complete the installation are incidental.