PROJECT QUESTION: What work needs to be done on temp system A? Only found a note in the plans about pigtails.

Question:
What work needs to be done on temp system A? Only found a note in the plans about pigtails.

Response:
See special provisions SS-4.2 for Temporary Signal System A. Contractor is responsible to keep the existing signal operational during construction.