Hennepin County

Welcome, Guest!
Log in | Employee Login | License
 

Messages

PROJECT QUESTION: Unsure if temporary bypass can be eliminated with current design, so why accommodate 3 dog houses? Can MH11A be built as shown, then build up to 11C when the road is closed and bypass to 11C while making the connection?

Question:
Unsure if temporary bypass can be eliminated with current design, so why accommodate 3 dog houses? Can MH11A be built as shown, then build up to 11C when the road is closed and bypass to 11C while making the connection?

Response:
Work assumed to be performed during the roadway closure south of Covington Terrace may be performed outside of the road closure timeframe only if two lanes of traffic are maintained on CSAH 101.