PROJECT QUESTION: Regarding section S-37.1 what vertical and horizontal channel dimensions must be maintained during - open channel - conditions?

QUESTION:
Regarding section S-37.1 what vertical and horizontal channel dimensions must be maintained during - open channel - conditions?

ANSWER:
If construction operations modify the existing channel such that the horizontal or vertical clearance is less than existing conditions, the channel shall be closed to water traffic.