PROJECT QUESTION: Will the county be furnishing traffic control plans for the detour in a future addendum?

Question:
Will the county be furnishing traffic control plans for the detour in a future addendum?

Answer: No. Section SB-12.1(B) states the following:

If traffic control layouts are not present in the Plan, or the Contractor modifies the layout or sequence from the Plan, the Contractor shall submit the proposed traffic control layout to the Engineer, for approval, at least fourteen (14) days prior to the start of construction. At least 24 hours prior to placement, all traffic control devices shall be available on the Project for inspection by the Engineer. The Contractor shall modify his/her proposed traffic control layout and/or devices as deemed necessary by the Engineer.