PROJECT QUESTION-Is Phase 1, Stage 1 an acceptable winter condition?

Question:
Is Phase 1, Stage 1 an acceptable winter condition?

Answer:
Yes, however the project intent is for limited user impacts, therefore this phase and stage was not intended to last more than a few weeks. As such the contactor should notify the Project Engineer of intent to use this phase one month prior such that City of Minneapolis and Hennepin County snow removal operations staff can plan accordingly.