PROJECT QUESTION: Who will remove the 850 railroad ties for this project? If there is a railroad contractor conducting this work, should the item be to dispose of railroad ties instead of remove?

Question: Who will remove the 850 railroad ties for this project? If there is a railroad contractor conducting this work, should the item be to dispose of railroad ties instead of remove?

Response: The BNSF will identify poor quality railroad ties as a part of the shoofly construction. The BNSF be responsible to disassemble ties from the rail and leave ties on south half of railroad corridor as a part of the shoofly construction. The scope of work for pay item 2104.509 Remove Railroad Tie is to collect ties from rail corridor and dispose of them per all applicable laws and regulations.