PROJECT QUESTION: : In the description of the dirt work for alternate #2 on sheets 26 and 28, 3.1 says to add topsoil borrow to achieve the median section as detailed on sheet 48. It appears this sheet reference may be incorrect, which detail on which sheet does this refer to?

Question: In the description of the dirt work for alternate #2 on sheets 26 and 28, 3.1 says to add topsoil borrow to achieve the median section as detailed on sheet 48. It appears this sheet reference may be incorrect, which detail on which sheet does this refer to?

Response: This note should call out ‘Sheet 47’. For clarification, Note ‘3.1. ADD TOPSOIL BORROW AS NEEDED TO ACHIEVE MEDIAN SECTION AS DETAILED ON SHEET 48.’ Should refer to Sheet 47.