PROJECT QUESTION: Sheet B5 Key Notes states the proposed pile lay-out is designed for 59.2 Kip working loads. What if the pre-cast supplier loads change this and are not in line with the pile shaft/starter sections assumptions outlined in SB-11?

Question:
Sheet B5 Key Notes states the proposed pile lay-out is designed for 59.2 Kip working loads. What if the pre-cast supplier loads change this and are not in line with the pile shaft/starter sections assumptions outlined in SB-11?

Response:
This design load is the load that will need to be utilized for bidding. If the contractor's design results in a different load, this modification will need to be handled under Section 1402- Contract Revisions.