PROJECT QUESTION: What are the Start date and completion date of the project?

Question: What are the Start date and completion date of the project?

Answer: See in the Division ?S? specifications Section 29 (1806) Determination and Extension of Contract Time:

S-29 (1806) DETERMINATION AND EXTENSION OF CONTRACT TIME
REVISED 12/02/16
S-29.1 Contractor must start construction operations by October 1, 2017, or no later than eight Calendar days after the date of Notice Contract Approval, whichever is later. Contractor must not begin construction operations before contract approval.
S-29.2 Contractor must complete all work required under this Contract, except maintenance work and Final Clean Up, on or before June 30, 2018.