PROJECT QUESTION: Could the County update us on when the anticipated public utility relocations per plan pages 15-19 are planned to start/finish? Has there been any communication between the utilities and the County regarding this?

Q: Could the County update us on when the anticipated public utility relocations per plan pages 15-19 are planned to start/finish? Has there been any communication between the utilities and the County regarding this?

A: The public utilities (watermain) are happening with the project. The private utilities have already started relocating in advance of the project, but some might have to wait until construction starts and coordinate with the contractor.