PROJECT QUESTION: Can the vertical elevation of the watermain relocation be modified from the plans by the contractor (through a submittal process) - long as 8 feet minimum of final cover is established over the pipe in all areas?

Q: Can the vertical elevation of the watermain relocation be modified from the plans by the contractor (through a submittal process) - long as 8 feet minimum of final cover is established over the pipe in all areas?

A: Modifications to the watermain alignment and elevation may be proposed by the Contractor for consideration, review and approval by the Engineer after contract award.