PROJECT QUESTION: Why the bid was extended for a week?

Q: Why the bid was extended for a week?

A: We have a number of outstanding questions from contractors we have not addressed yet, some of which require revisions via addendum. The county policy is to release addendums (other than those to extend the bid date) no later than 4 days business days prior to bid opening. Because we were not able to meet that requirement here, we extended the bid opening. The county only opens bids once a week, therefore extending the bid opening one week was the minimum duration we could move it.