PROJECT QUESTION: What is the substantial completion date for the project?

Q: What is the substantial completion date for the project?

A: As noted in S-42.4 of the special provisions, the substantial completion date is August 31, 2019. Please refer to S-42 in the special provisions for a list of all the interim completion dates and the final completion date for the project.