Last ModifiedSubjectPosted By
10/29/2020 3:55 PMOn sheet SS-2, does the vertical pole 7 remain inplace? Just F&I a new mast arm for this pole? This pole also calls for (2) new 2” Conduits for lighting into the existing signal pole foundation. Is this correct? Is the conduit from HH 4 to HH 1 existing or to be new? Drager, Eric M
10/29/2020 11:57 AMCan I get information that was covered in the pre-bid conference?Drager, Eric M
10/28/2020 5:13 PMFor bid item “INSTALL SIGN COLLAR”, what is the cost for the sign collars? Also, for the signs that require a 30” precast foundation as per MPLS. Std. plate TRAF-5070, is the entire precast foundation supplied by the city, or is it only the collar, pipe, set crew, & rebar assembly, and the contractor is responsible for precasting the foundations?Drager, Eric M
10/28/2020 5:06 PMIn the Minneapolis supplemental specifications division WM – Water Distribution Systems Supplemental Specifications – 3.19A, is the work we are doing on this project required to be done by a plumber or is this exempt? Drager, Eric M
10/28/2020 5:05 PMWhat standard plate references “Reconstruct Water Manhole”? – I did not find where it defines the extent of each reconstruct in the plans, the project specifications, or the Minneapolis supplemental specifications. Drager, Eric M
10/28/2020 5:04 PMUnder S-34.2, what is the cost for the city licenses and permits for electrical or water work on this project? Drager, Eric M
10/28/2020 5:02 PMUnder special provision S-34.2, it states “The contractor shall be responsible for the payment of all inspection fees charged by the City of Minneapolis Inspections Department in association with work performed on this project.” – Is this correct, and if so how does one determine their scope of work and fees associated for the duration of the project? Drager, Eric M
10/01/2020 4:16 PMPre-bidding conferenceDrager, Eric M