2151001 - CSAH 15 & 19 INTERSECTION RECONSTRUCTIONMeyer Contracting Inc. Thomas & Sons Construction, INC. Pember Companies, Inc 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLUMP SUM0.9$57,194.48$51,475.03$210,500.00$189,450.00$139,000.00$125,100.00
2031.502FIELD OFFICE TYPE DEACH0.9$23,102.49$20,792.24$50,000.00$45,000.00$9,000.00$8,100.00
2102.503PAVEMENT MARKING REMOVALLIN FT3,123$0.80$2,498.40$1.10$3,435.30$1.05$3,279.15
2102.518PAVEMENT MARKING REMOVALSQ FT96$10.00$960.00$3.30$316.80$3.20$307.20
2104.502REMOVE DRAINAGE STRUCTUREEACH8$592.00$4,736.00$1,250.00$10,000.00$975.00$7,800.00
2104.502SALVAGE SIGN TYPE CEACH1$40.00$40.00$155.00$155.00$53.00$53.00
2104.502REMOVE SIGNAL SYSTEMEACH1$5,121.00$5,121.00$4,700.00$4,700.00$12,000.00$12,000.00
2104.502REMOVE SIGN TYPE CEACH29$40.00$1,160.00$55.00$1,595.00$53.00$1,537.00
2104.503SAWING BIT PAVEMENT (FULL DEPTH)LIN FT468$2.00$936.00$9.00$4,212.00$8.00$3,744.00
2104.503REMOVE SEWER PIPE (STORM)LIN FT710$46.00$32,660.00$35.00$24,850.00$32.00$22,720.00
2104.503REMOVE CURB & GUTTERLIN FT1,035$4.60$4,761.00$10.00$10,350.00$10.50$10,867.50
2104.504REMOVE PAVEMENTSQ YD4,009$14.50$58,130.50$23.00$92,207.00$22.00$88,198.00
2104.504REMOVE CONCRETE DRIVEWAY PAVEMENTSQ YD103$20.75$2,137.25$24.00$2,472.00$16.10$1,658.30
2104.518REMOVE BITUMINOUS PAVEMENTSQ FT772$1.30$1,003.60$3.00$2,316.00$1.65$1,273.80
2104.518REMOVE CONCRETE NOSESQ FT239$1.50$358.50$3.00$717.00$1.65$394.35
2104.518REMOVE CONCRETE WALKSQ FT5,661$0.95$5,377.95$1.50$8,491.50$1.55$8,774.55
2105.601DEWATERINGLUMP SUM1$28,169.00$28,169.00$1.00$1.00$15,000.00$15,000.00
2105.607EXCAVATION SPECIALCU YD460$47.75$21,965.00$15.00$6,900.00$35.00$16,100.00
2105.609HAUL & DISPOSE OF CONTAMINATED SOILTON645$62.00$39,990.00$42.50$27,412.50$42.00$27,090.00
2106.507GRANULAR EMBANKMENT (CV)CU YD1,367$61.25$83,728.75$52.75$72,109.25$57.00$77,919.00
2106.507EXCAVATION - COMMONCU YD1,187$61.75$73,297.25$57.50$68,252.50$58.00$68,846.00
2106.507EXCAVATION - SUBGRADECU YD1,367$44.75$61,173.25$37.50$51,262.50$58.00$79,286.00
2123.610STREET SWEEPER (WITH PICKUP BROOM)HOUR100$150.00$15,000.00$155.00$15,500.00$130.00$13,000.00
2211.507AGGREGATE BASE (CV) CLASS 5CU YD1,745$75.25$131,311.25$68.00$118,660.00$83.00$144,835.00
2231.604BITUMINOUS PATCHSQ YD110$100.00$11,000.00$115.00$12,650.00$120.00$13,200.00
2232.504MILL BITUMINOUS SURFACESQ YD130$10.50$1,365.00$12.00$1,560.00$11.15$1,449.50
2360.509TYPE SP 12.5 WEARING COURSE MIX (3;C)TON813$94.50$76,828.50$105.00$85,365.00$100.45$81,665.85
2360.509TYPE SP 12.5 NON WEAR COURSE MIX (3;B)TON618$84.75$52,375.50$95.00$58,710.00$90.15$55,712.70
2503.50318" RC PIPE SEWER CLASS IIILIN FT49$117.50$5,757.50$120.00$5,880.00$130.00$6,370.00
2503.50321" RC PIPE SEWER CLASS IIILIN FT196$127.00$24,892.00$130.00$25,480.00$135.00$26,460.00
2503.50315" RC PIPE SEWER CLASS VLIN FT261$86.75$22,641.75$110.00$28,710.00$120.00$31,320.00
2503.50324" RC PIPE SEWER CLASS IIILIN FT99$133.00$13,167.00$150.00$14,850.00$155.00$15,345.00
2503.602CONNECT TO EXISTING STORM SEWEREACH2$791.50$1,583.00$2,200.00$4,400.00$1,400.00$2,800.00
2506.502CASTING ASSEMBLYEACH9$1,255.00$11,295.00$1,200.00$10,800.00$745.00$6,705.00
2506.503CONST DRAINAGE STRUCTURE DES 54-4020LIN FT5.2$1,331.00$6,921.20$1,150.00$5,980.00$870.00$4,524.00
2506.503CONST DRAINAGE STRUCTURE DESIGN GLIN FT4$921.50$3,686.00$675.00$2,700.00$592.00$2,368.00
2506.503CONST DRAINAGE STRUCTURE DESIGN FLIN FT43.2$784.50$33,890.40$650.00$28,080.00$425.00$18,360.00
2506.503CONST DRAINAGE STRUCTURE DES 78-4020LIN FT6.9$2,010.00$13,869.00$2,250.00$15,525.00$1,200.00$8,280.00
2506.602CONNECT INTO EXISTING DRAINAGE STRUCTUREEACH1$2,339.00$2,339.00$2,000.00$2,000.00$1,300.00$1,300.00
2521.5184" CONCRETE WALKSQ FT7,835$6.40$50,144.00$9.50$74,432.50$8.10$63,463.50
2521.5186" CONCRETE WALKSQ FT971$12.50$12,137.50$18.50$17,963.50$17.45$16,943.95
2531.503CONCRETE CURB & GUTTER DESIGN B624LIN FT1,148$45.50$52,234.00$51.85$59,523.80$53.00$60,844.00
2531.5048" CONCRETE DRIVEWAY PAVEMENTSQ YD16$94.50$1,512.00$140.00$2,240.00$135.00$2,160.00
2531.618TRUNCATED DOMESSQ FT123$45.00$5,535.00$81.00$9,963.00$65.00$7,995.00
2533.503PORTABLE PRECAST CONC BARRIER DES 8337LIN FT275$15.00$4,125.00$16.00$4,400.00$15.00$4,125.00
2533.503RELOCATE PORT PRECAST CONC BAR DES 8337LIN FT1,165$4.80$5,592.00$5.50$6,407.50$5.30$6,174.50
2554.615RELOCATE IMPACT ATTENUATORASSEMBLY18$500.00$9,000.00$660.00$11,880.00$635.00$11,430.00
2554.615IMPACT ATTENUATORASSEMBLY4$1,400.00$5,600.00$2,000.00$8,000.00$1,910.00$7,640.00
2563.601TRAFFIC CONTROLLUMP SUM0.9$63,333.33$57,000.00$60,000.00$54,000.00$136,665.00$122,998.50
2563.601TRAFFIC CONTROL SUPERVISORLUMP SUM1$10,000.00$10,000.00$6,000.00$6,000.00$5,000.00$5,000.00
2563.602TUBE DELINEATOREACH383$30.00$11,490.00$33.00$12,639.00$31.80$12,179.40
2563.602PORTABLE CONCRETE BARRIER DELINEATOREACH11$8.00$88.00$12.00$132.00$10.60$116.60
2563.610POLICE OFFICERHOUR20$100.00$2,000.00$95.00$1,900.00$140.00$2,800.00
2563.613PORTABLE CHANGEABLE MESSAGE SIGNUNIT DAY100$5.00$500.00$55.00$5,500.00$53.00$5,300.00
2563.618CONSTRUCTION SIGN-SPECIALSQ FT513$5.00$2,565.00$16.50$8,464.50$15.90$8,156.70
2564.502INSTALL SIGN TYPE CEACH1$250.00$250.00$82.00$82.00$80.00$80.00
2564.518SIGN PANELS TYPE CSQ FT133$55.00$7,315.00$47.00$6,251.00$44.55$5,925.15
2565.501EMERGENCY VEHICLE PREEMPTION SYSTEMLUMP SUM1$6,275.00$6,275.00$6,800.00$6,800.00$7,000.00$7,000.00
2565.516TRAFFIC CONTROL SIGNAL SYSTEMSYSTEM1$230,510.00$230,510.00$255,000.00$255,000.00$244,075.00$244,075.00
2565.616TEMPORARY SIGNAL SYSTEMSYSTEM1$78,270.00$78,270.00$86,000.00$86,000.00$83,000.00$83,000.00
2573.501EROSION CONTROL SUPERVISORLUMP SUM1$2,999.00$2,999.00$3,500.00$3,500.00$2,000.00$2,000.00
2573.502STORM DRAIN INLET PROTECTIONEACH16$120.00$1,920.00$195.00$3,120.00$130.00$2,080.00
2573.503SEDIMENT CONTROL LOG TYPE ROCKLIN FT100$3.80$380.00$16.00$1,600.00$15.00$1,500.00
2574.508FERTILIZER TYPE 3POUND50$0.50$25.00$1.00$50.00$3.00$150.00
2575.504EROSION CONTROL BLANKETS CATEGORY 3NSQ YD200$2.50$500.00$4.00$800.00$4.20$840.00
2575.504SODDING TYPE LAWNSQ YD75$15.00$1,125.00$20.00$1,500.00$16.00$1,200.00
2575.508SEED MIXTURE 25-151POUND10$3.50$35.00$8.00$80.00$31.50$315.00
2575.523RAPID STABILIZATION METHOD 3M GALLON2$600.00$1,200.00$700.00$1,400.00$1,050.00$2,100.00
2582.5034" SOLID LINE MULTI COMP GR INLIN FT2,122$1.50$3,183.00$1.65$3,501.30$1.60$3,395.20
2582.5034" BROKEN LINE MULTI COMP GR INLIN FT360$1.50$540.00$1.65$594.00$1.60$576.00
2582.5034" DBLE SOLID LINE MULTI COMP GR INLIN FT1,295$3.00$3,885.00$3.30$4,273.50$3.20$4,144.00
2582.5036" SOLID LINE MULTI COMP GR INLIN FT2,350$2.20$5,170.00$2.45$5,757.50$2.35$5,522.50
2582.50324" SOLID LINE MULTI COMP GR INLIN FT75$16.00$1,200.00$17.50$1,312.50$17.00$1,275.00
2582.5034" SOLID LINE PAINTLIN FT400$1.50$600.00$2.00$800.00$1.60$640.00
2582.5034" DBLE SOLID LINE PAINTLIN FT200$3.00$600.00$4.00$800.00$3.20$640.00
2582.5034" BROKEN LINE PAINTLIN FT100$1.50$150.00$2.00$200.00$1.60$160.00
2582.518CROSSWALK PREF THERMO GR INSQ FT612$12.75$7,803.00$14.25$8,721.00$13.50$8,262.00
2582.518PAVT MSSG PREF THERMO GR INSQ FT195$24.00$4,680.00$26.40$5,148.00$25.50$4,972.50
 Totals for project 2151001 $1,516,530.32 $1,743,791.95 $1,730,922.40
 
Contract Total:$1,516,530.32$1,743,791.95$1,730,922.40