2951600 - CSAH 101 from CSAH 6 to 30th Ave NShafer Contracting Company., Inc. S. R. Weidema, Inc. Veit & Company, Inc. Park Construction Company Ames Construction, Inc Mathiowetz Construction Company 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLS1$650,000.00$650,000.00$485,718.13$485,718.13$700,000.00$700,000.00$644,344.00$644,344.00$765,000.00$765,000.00$2,582,372.00$2,582,372.00
2031.501FIELD OFFICE TYPE DEACH1$30,000.00$30,000.00$37,200.00$37,200.00$28,000.00$28,000.00$65,300.00$65,300.00$32,000.00$32,000.00$40,000.00$40,000.00
2031.503FIELD LABORATORY TYPE DEACH1$15,000.00$15,000.00$25,600.00$25,600.00$28,000.00$28,000.00$39,000.00$39,000.00$11,000.00$11,000.00$35,000.00$35,000.00
2041.610TRAINEESHOUR3,000$0.01$30.00$1.00$3,000.00$1.00$3,000.00$1.00$3,000.00$1.00$3,000.00$0.25$750.00
2101.511CLEARING AND GRUBBINGLUMP SUM1$35,000.00$35,000.00$30,500.00$30,500.00$31,000.00$31,000.00$29,200.00$29,200.00$150,000.00$150,000.00$87,000.00$87,000.00
2101.603ROOT CUTTINGLIN FT200$5.00$1,000.00$10.00$2,000.00$10.75$2,150.00$6.05$1,210.00$7.00$1,400.00$10.00$2,000.00
2102.501PAVEMENT MARKING REMOVALSQ FT2,000$1.50$3,000.00$1.60$3,200.00$1.45$2,900.00$1.55$3,100.00$1.35$2,700.00$1.20$2,400.00
2102.502PAVEMENT MARKING REMOVALLIN FT10,000$0.50$5,000.00$0.40$4,000.00$0.50$5,000.00$0.18$1,800.00$0.45$4,500.00$0.40$4,000.00
2103.501BUILDING REMOVAL CLUMP SUM1$15,000.00$15,000.00$14,515.00$14,515.00$10,500.00$10,500.00$10,200.00$10,200.00$10,000.00$10,000.00$12,000.00$12,000.00
2103.501BUILDING REMOVAL BLUMP SUM1$15,000.00$15,000.00$12,615.00$12,615.00$11,000.00$11,000.00$9,980.00$9,980.00$10,000.00$10,000.00$12,000.00$12,000.00
2103.501BUILDING REMOVAL DLUMP SUM1$0.01$0.01$1,750.00$1,750.00$2,700.00$2,700.00$1.00$1.00$1.00$1.00$2,500.00$2,500.00
2103.501BUILDING REMOVAL ALUMP SUM1$0.01$0.01$1,750.00$1,750.00$2,500.00$2,500.00$1.00$1.00$1.00$1.00$2,500.00$2,500.00
2104.501REMOVE PIPE SEWERSL F3,916$10.00$39,160.00$9.00$35,244.00$8.00$31,328.00$19.00$74,404.00$15.00$58,740.00$7.00$27,412.00
2104.501REMOVE RETAINING WALLLIN FT408$10.00$4,080.00$5.30$2,162.40$6.00$2,448.00$10.00$4,080.00$13.00$5,304.00$4.00$1,632.00
2104.501REMOVE STEEL CASINGLIN FT308$10.00$3,080.00$14.50$4,466.00$13.00$4,004.00$6.60$2,032.80$15.00$4,620.00$5.00$1,540.00
2104.501REMOVE WOOD RETAINING WALLLIN FT332$20.00$6,640.00$5.90$1,958.80$4.00$1,328.00$8.25$2,739.00$12.00$3,984.00$5.00$1,660.00
2104.501REMOVE SANITARY SERVICE PIPELIN FT378$10.00$3,780.00$11.20$4,233.60$7.00$2,646.00$10.60$4,006.80$12.00$4,536.00$3.00$1,134.00
2104.501REMOVE PIPE CULVERTSLIN FT281$10.00$2,810.00$5.60$1,573.60$7.00$1,967.00$18.60$5,226.60$15.00$4,215.00$7.00$1,967.00
2104.501REMOVE WOOD FENCELIN FT1,027$5.00$5,135.00$3.20$3,286.40$4.00$4,108.00$8.30$8,524.10$3.00$3,081.00$3.00$3,081.00
2104.501REMOVE WATER MAINL F4,785$10.00$47,850.00$5.90$28,231.50$7.00$33,495.00$14.20$67,947.00$13.00$62,205.00$3.00$14,355.00
2104.501REMOVE CURB AND GUTTERLIN FT11,778$3.00$35,334.00$2.00$23,556.00$2.50$29,445.00$1.95$22,967.10$1.50$17,667.00$3.25$38,278.50
2104.501REMOVE CHAIN LINK FENCELIN FT748$5.00$3,740.00$2.70$2,019.60$3.00$2,244.00$2.60$1,944.80$2.00$1,496.00$2.50$1,870.00
2104.501REMOVE SEWER PIPE (SANITARY)LIN FT1,140$10.00$11,400.00$15.00$17,100.00$8.00$9,120.00$12.70$14,478.00$13.00$14,820.00$3.00$3,420.00
2104.501REMOVE BITUMINOUS CURBLIN FT1,689$2.00$3,378.00$1.65$2,786.85$2.50$4,222.50$1.65$2,786.85$1.00$1,689.00$2.50$4,222.50
2104.501REMOVE GUARD RAILLIN FT1,085$5.40$5,859.00$3.00$3,255.00$6.00$6,510.00$4.00$4,340.00$5.00$5,425.00$2.50$2,712.50
2104.501REMOVE WATER SERVICE PIPELIN FT421$10.00$4,210.00$7.40$3,115.40$7.00$2,947.00$8.95$3,767.95$12.00$5,052.00$3.00$1,263.00
2104.503REMOVE CONCRETE DRIVEWAY PAVEMENTSQ FT1,990$1.00$1,990.00$0.15$298.50$0.30$597.00$0.49$975.10$1.00$1,990.00$0.70$1,393.00
2104.503REMOVE BITUMINOUS DRIVEWAY PAVEMENTSQ FT27,063$0.40$10,825.20$0.15$4,059.45$0.30$8,118.90$0.28$7,577.64$0.70$18,944.10$0.25$6,765.75
2104.503REMOVE BITUMINOUS PAVEMENTSQ FT476,813$0.25$119,203.25$0.25$119,203.25$0.10$47,681.30$0.23$109,666.99$0.35$166,884.55$0.30$143,043.90
2104.503REMOVE BITUMINOUS WALKSQ FT33,298$0.50$16,649.00$0.10$3,329.80$0.30$9,989.40$0.28$9,323.44$0.30$9,989.40$0.25$8,324.50
2104.503REMOVE CONCRETE WALKS F27,798$0.50$13,899.00$0.11$3,057.78$0.30$8,339.40$0.29$8,061.42$0.70$19,458.60$0.70$19,458.60
2104.509REMOVE CONTROLLER FOUNDATIONEACH2$1,000.00$2,000.00$500.00$1,000.00$600.00$1,200.00$406.00$812.00$250.00$500.00$100.00$200.00
2104.509REMOVE MANHOLEEACH6$250.00$1,500.00$245.00$1,470.00$150.00$900.00$458.00$2,748.00$500.00$3,000.00$500.00$3,000.00
2104.509REMOVE CASTINGEACH2$250.00$500.00$115.00$230.00$17.00$34.00$64.90$129.80$200.00$400.00$200.00$400.00
2104.509REMOVE CURB STOP & BOXEACH10$100.00$1,000.00$95.00$950.00$7.00$70.00$12.40$124.00$200.00$2,000.00$100.00$1,000.00
2104.509REMOVE LIGHT POLEEACH1$235.39$235.39$300.00$300.00$265.00$265.00$684.00$684.00$235.39$235.39$236.00$236.00
2104.509REMOVE MAST ARM FOUNDATIONEACH8$3,000.00$24,000.00$550.00$4,400.00$600.00$4,800.00$406.00$3,248.00$350.00$2,800.00$1,000.00$8,000.00
2104.509REMOVE HANDHOLEEACH31$131.38$4,072.78$150.00$4,650.00$145.00$4,495.00$171.00$5,301.00$150.00$4,650.00$132.00$4,092.00
2104.509REMOVE DRAINAGE STRUCTUREEACH44$250.00$11,000.00$220.00$9,680.00$160.00$7,040.00$227.00$9,988.00$500.00$22,000.00$400.00$17,600.00
2104.509REMOVE MISCELLANEOUS STRUCTURESEACH3$500.00$1,500.00$500.00$1,500.00$300.00$900.00$457.00$1,371.00$500.00$1,500.00$100.00$300.00
2104.513SAWING BITUMINOUS PAVEMENTLIN FT461$5.00$2,305.00$2.30$1,060.30$3.00$1,383.00$0.78$359.58$5.00$2,305.00$2.20$1,014.20
2104.513SAWING BITUMINOUS PAVEMENT (FULL DEPTH)LIN FT2,751$3.00$8,253.00$2.85$7,840.35$3.00$8,253.00$0.78$2,145.78$5.00$13,755.00$2.20$6,052.20
2104.521SALVAGE CHAIN LINK FENCELIN FT80$10.00$800.00$4.35$348.00$4.00$320.00$2.65$212.00$3.00$240.00$3.00$240.00
2104.523SALVAGE CASTING (SANITARY)EACH6$250.00$1,500.00$115.00$690.00$100.00$600.00$64.90$389.40$200.00$1,200.00$150.00$900.00
2104.523SALVAGE HYDRANTEACH10$1,000.00$10,000.00$330.00$3,300.00$140.00$1,400.00$618.00$6,180.00$1,200.00$12,000.00$1,000.00$10,000.00
2104.523SALVAGE GATE VALVE & BOXEACH24$500.00$12,000.00$280.00$6,720.00$140.00$3,360.00$927.00$22,248.00$600.00$14,400.00$200.00$4,800.00
2104.523SALVAGE SIGNEACH196$45.00$8,820.00$19.00$3,724.00$50.00$9,800.00$16.10$3,155.60$20.00$3,920.00$15.00$2,940.00
2104.523SALVAGE VALVEEACH1$500.00$500.00$370.00$370.00$140.00$140.00$618.00$618.00$600.00$600.00$100.00$100.00
2104.601RELOCATE YARD LIGHTLUMP SUM1$574.29$574.29$350.00$350.00$600.00$600.00$279.00$279.00$1,000.00$1,000.00$750.00$750.00
2104.603ABANDON WATER MAINLIN FT1,150$10.00$11,500.00$7.75$8,912.50$6.00$6,900.00$2.15$2,472.50$13.00$14,950.00$5.00$5,750.00
2104.603ABANDON PIPE SEWERLIN FT81$10.00$810.00$25.00$2,025.00$11.00$891.00$6.10$494.10$15.00$1,215.00$25.00$2,025.00
2105.501COMMON EXCAVATION (P)CU YD75,780$6.00$454,680.00$9.35$708,543.00$8.00$606,240.00$8.90$674,442.00$13.00$985,140.00$9.00$682,020.00
2105.507SUBGRADE EXCAVATION (P)CU YD13,265$2.00$26,530.00$8.85$117,395.25$10.00$132,650.00$8.40$111,426.00$13.00$172,445.00$9.00$119,385.00
2105.522SELECT GRANULAR BORROW (CV) (P)CU YD27,422$15.00$411,330.00$16.30$446,978.60$12.25$335,919.50$24.10$660,870.20$20.00$548,440.00$20.50$562,151.00
2105.543STABILIZING AGGREGATETON300$25.00$7,500.00$32.00$9,600.00$25.00$7,500.00$30.40$9,120.00$15.00$4,500.00$23.00$6,900.00
2105.603TEMPORARY WALKLIN FT800$2.00$1,600.00$5.00$4,000.00$3.00$2,400.00$4.65$3,720.00$3.00$2,400.00$2.50$2,000.00
2105.603TEMPORARY DRIVEWAYLIN FT800$8.00$6,400.00$31.00$24,800.00$6.00$4,800.00$6.95$5,560.00$7.00$5,600.00$11.50$9,200.00
2105.604GEOTEXTILE FABRIC TYPE IVSQ YD165$10.00$1,650.00$1.80$297.00$1.50$247.50$2.90$478.50$4.01$661.65$2.00$330.00
2105.607HAUL & DISPOSE OF CONTAMINATED MATERIALCU YD500$40.00$20,000.00$31.00$15,500.00$30.50$15,250.00$55.00$27,500.00$29.00$14,500.00$50.00$25,000.00
2118.501AGGREGATE SURFACING CLASS 2TON5$100.00$500.00$70.00$350.00$50.00$250.00$92.80$464.00$35.00$175.00$30.00$150.00
2123.610STREET SWEEPER (WITH PICKUP BROOM)HOUR200$100.00$20,000.00$147.00$29,400.00$150.00$30,000.00$125.00$25,000.00$100.00$20,000.00$135.00$27,000.00
2130.501WATERM GALLONS320$25.00$8,000.00$35.00$11,200.00$120.00$38,400.00$33.00$10,560.00$30.00$9,600.00$20.00$6,400.00
2131.502CALCIUM CHLORIDE SOLUTIONGALLONS25,000$1.00$25,000.00$1.25$31,250.00$1.00$25,000.00$1.05$26,250.00$0.05$1,250.00$1.11$27,750.00
2211.503AGGREGATE BASE (CV) CLASS 5 (P)CU YD2,186$20.00$43,720.00$21.00$45,906.00$26.00$56,836.00$43.50$95,091.00$16.00$34,976.00$27.00$59,022.00
2211.503AGGREGATE BASE (CV) CLASS 6 (P)CU YD13,836$20.00$276,720.00$23.15$320,303.40$24.00$332,064.00$31.40$434,450.40$18.00$249,048.00$28.75$397,785.00
2231.501BITUMINOUS PATCHING MIXTURETON200$135.00$27,000.00$160.00$32,000.00$145.00$29,000.00$138.00$27,600.00$135.00$27,000.00$135.00$27,000.00
2232.501MILL BITUMINOUS SURFACESQ YD2,643$2.25$5,946.75$2.35$6,211.05$2.75$7,268.25$1.55$4,096.65$2.25$5,946.75$2.25$5,946.75
2357.502BITUMINOUS MATERIAL FOR TACK COATGALLONS10,165$3.00$30,495.00$3.00$30,495.00$3.25$33,036.25$3.05$31,003.25$3.00$30,495.00$3.00$30,495.00
2360.501TYPE SP 12.5 WEARING COURSE MIXTURE (4,F)TON15,903$73.00$1,160,919.00$73.75$1,172,846.25$78.50$1,248,385.50$74.60$1,186,363.80$73.00$1,160,919.00$73.00$1,160,919.00
2360.502TYPE SP 19.0 NON WEARING COURSE MIXTURE (4,B)TON25,317$61.00$1,544,337.00$61.00$1,544,337.00$65.50$1,658,263.50$62.30$1,577,249.10$61.00$1,544,337.00$61.00$1,544,337.00
2401.601FOUNDATION PREPARATION WALL 6LUMP SUM1$40,000.00$40,000.00$40,500.00$40,500.00$43,000.00$43,000.00$42,600.00$42,600.00$18,000.00$18,000.00$40,000.00$40,000.00
2401.601FOUNDATION PREPARATION WALL 2LUMP SUM1$40,000.00$40,000.00$51,000.00$51,000.00$43,000.00$43,000.00$42,600.00$42,600.00$55,000.00$55,000.00$40,000.00$40,000.00
2401.601FOUNDATION PREPARATION WALL 5LUMP SUM1$80,000.00$80,000.00$91,000.00$91,000.00$86,000.00$86,000.00$85,100.00$85,100.00$140,000.00$140,000.00$80,000.00$80,000.00
2401.601FOUNDATION PREPARATION WALL 1LUMP SUM1$130,000.00$130,000.00$116,150.00$116,150.00$140,000.00$140,000.00$138,300.00$138,300.00$140,000.00$140,000.00$130,000.00$130,000.00
2401.601FOUNDATION PREPARATION WALL 3LUMP SUM1$45,000.00$45,000.00$71,000.00$71,000.00$48,000.00$48,000.00$47,900.00$47,900.00$80,000.00$80,000.00$45,000.00$45,000.00
2401.601FOUNDATION PREPARATION WALL 7LUMP SUM1$85,000.00$85,000.00$86,000.00$86,000.00$91,000.00$91,000.00$90,400.00$90,400.00$80,000.00$80,000.00$85,000.00$85,000.00
2411.501STRUCTURAL CONCRETE (1A43)CU YD2,071.1$350.00$724,885.00$353.00$731,098.30$375.00$776,662.50$410.00$849,151.00$375.00$776,662.50$385.00$797,373.50
2411.501STRUCTURAL CONCRETE (3Y43)CU YD3,031.2$420.00$1,273,104.00$404.00$1,224,604.80$550.00$1,667,160.00$452.00$1,370,102.40$400.00$1,212,480.00$425.00$1,288,260.00
2411.511STRUCTURE EXCAVATION CLASS ECU YD12,639$7.00$88,473.00$10.20$128,917.80$12.00$151,668.00$12.60$159,251.40$23.00$290,697.00$9.00$113,751.00
2411.521GRANULAR BACKFILL (CV)CU YD12,228$15.00$183,420.00$19.10$233,554.80$15.00$183,420.00$25.60$313,036.80$23.00$281,244.00$19.00$232,332.00
2411.541REINFORCEMENT BARSPOUND182,906$0.85$155,470.10$1.00$182,906.00$0.90$164,615.40$0.90$164,615.40$1.10$201,196.60$0.85$155,470.10
2411.541REINFORCEMENT BARS (EPOXY COATED)POUND321,975$0.95$305,876.25$1.10$354,172.50$1.00$321,975.00$1.00$321,975.00$1.30$418,567.50$0.95$305,876.25
2411.601DRAINAGE SYSTEMLUMP SUM1$20,000.00$20,000.00$43,000.00$43,000.00$27,000.00$27,000.00$21,300.00$21,300.00$50,000.00$50,000.00$20,000.00$20,000.00
2411.603CONCRETE PARAPET WALLLIN FT4,094$75.00$307,050.00$61.00$249,734.00$80.00$327,520.00$79.80$326,701.20$50.00$204,700.00$75.00$307,050.00
2411.618ARCHITECTURAL SURFACE TREATMENT (P)SQ FT51,368$7.50$385,260.00$8.10$416,080.80$8.00$410,944.00$8.00$410,944.00$8.00$410,944.00$7.50$385,260.00
2411.618MODULAR BLOCK RETAINING WALLSQ FT588$35.00$20,580.00$30.50$17,934.00$37.00$21,756.00$27.80$16,346.40$38.00$22,344.00$32.00$18,816.00
2411.618ARCHITECTURAL COLR SYSTEM (P)SQ FT51,368$3.45$177,219.60$3.50$179,788.00$3.70$190,061.60$3.65$187,493.20$3.45$177,219.60$3.45$177,219.60
2411.618SPECIAL SURFACE FINISHSQ FT11,750$1.25$14,687.50$1.25$14,687.50$1.30$15,275.00$1.35$15,862.50$1.25$14,687.50$1.25$14,687.50
2451.607ROCK BEDDING (CV)CU YD100$40.00$4,000.00$53.25$5,325.00$53.00$5,300.00$58.10$5,810.00$50.00$5,000.00$40.00$4,000.00
2451.609AGGREGATE FOUNDATIONTON100$20.00$2,000.00$27.60$2,760.00$26.00$2,600.00$32.60$3,260.00$30.00$3,000.00$30.00$3,000.00
2452.507C-I-P CONCRETE PILING DELIVERED 12"LIN FT15,850$26.00$412,100.00$29.30$464,405.00$28.00$443,800.00$27.70$439,045.00$43.00$681,550.00$26.00$412,100.00
2452.508C-I-P CONCRETE PILING DRIVEN 12"LIN FT15,850$1.00$15,850.00$1.00$15,850.00$1.00$15,850.00$1.05$16,642.50$1.00$15,850.00$1.00$15,850.00
2452.519C-I-P CONC TEST PILE 35 FT LONG 12"EACH7$2,750.00$19,250.00$3,030.00$21,210.00$2,960.00$20,720.00$2,930.00$20,510.00$2,500.00$17,500.00$2,750.00$19,250.00
2452.519C-I-P CONC TEST PILE 25 FT LONG 12"EACH20$2,500.00$50,000.00$2,625.00$52,500.00$2,690.00$53,800.00$2,660.00$53,200.00$2,000.00$40,000.00$2,500.00$50,000.00
2452.519C-I-P CONC TEST PILE 45 FT LONG 12"EACH1$3,250.00$3,250.00$3,535.00$3,535.00$3,497.08$3,497.08$3,460.00$3,460.00$4,000.00$4,000.00$3,250.00$3,250.00
2452.519C-I-P CONC TEST PILE 40 FT LONG 12"EACH14$3,000.00$42,000.00$3,232.00$45,248.00$3,228.08$45,193.12$3,190.00$44,660.00$3,000.00$42,000.00$3,000.00$42,000.00
2501.51115" CS PIPE CULVERTLIN FT82$30.00$2,460.00$38.40$3,148.80$35.00$2,870.00$39.50$3,239.00$25.00$2,050.00$21.00$1,722.00
2501.51524" RC PIPE APRONEACH2$1,200.00$2,400.00$937.00$1,874.00$1,030.00$2,060.00$1,050.00$2,100.00$800.00$1,600.00$775.00$1,550.00
2501.51518" RC PIPE APRONEACH4$950.00$3,800.00$776.00$3,104.00$864.00$3,456.00$841.00$3,364.00$700.00$2,800.00$586.00$2,344.00
2501.51515" RC PIPE APRONEACH12$900.00$10,800.00$660.00$7,920.00$817.00$9,804.00$729.00$8,748.00$650.00$7,800.00$494.00$5,928.00
2501.51536" RC PIPE APRONEACH1$1,900.00$1,900.00$1,515.00$1,515.00$1,860.00$1,860.00$1,460.00$1,460.00$1,000.00$1,000.00$1,277.00$1,277.00
2501.56121" RC PIPE CULVERT DESIGN 3006LIN FT105$35.00$3,675.00$37.00$3,885.00$39.00$4,095.00$44.90$4,714.50$40.00$4,200.00$33.50$3,517.50
2501.56115" RC PIPE CULVERT DES 3006 CL IIILIN FT22$45.00$990.00$30.00$660.00$37.00$814.00$61.70$1,357.40$50.00$1,100.00$28.50$627.00
2502.5214" TP PIPE DRAINLIN FT273$10.00$2,730.00$7.00$1,911.00$3.00$819.00$3.40$928.20$8.00$2,184.00$3.50$955.50
2502.5414" PERF PE PIPE DRAINLIN FT15,276$6.00$91,656.00$3.50$53,466.00$2.24$34,218.24$5.25$80,199.00$6.00$91,656.00$5.50$84,018.00
2502.602YARD DRAINEACH1$2,000.00$2,000.00$300.00$300.00$329.03$329.03$1,660.00$1,660.00$500.00$500.00$750.00$750.00
2503.5118" PVC PIPE SEWERLIN FT993$30.00$29,790.00$31.35$31,130.55$28.00$27,804.00$48.80$48,458.40$75.00$74,475.00$25.00$24,825.00
2503.52128" SPAN RC PIPE-ARCH SEWER CLASS IIALIN FT375$61.00$22,875.00$64.15$24,056.25$71.00$26,625.00$95.30$35,737.50$75.00$28,125.00$62.50$23,437.50
2503.54124" RC PIPE SEWER DESIGN 3006LIN FT446.8$37.00$16,531.60$46.80$20,910.24$44.00$19,659.20$42.10$18,810.28$44.00$19,659.20$40.50$18,095.40
2503.54121" RC PIPE SEWER DESIGN 3006 CLASS IIILIN FT52$35.00$1,820.00$41.00$2,132.00$41.00$2,132.00$50.20$2,610.40$43.00$2,236.00$38.50$2,002.00
2503.54112" RC PIPE SEWER DESIGN 3006LIN FT17$50.00$850.00$28.40$482.80$32.00$544.00$31.80$540.60$35.00$595.00$28.00$476.00
2503.54142" RC PIPE SEWER DESIGN 3006 CLASS IIILIN FT240$85.00$20,400.00$90.50$21,720.00$98.00$23,520.00$128.00$30,720.00$93.00$22,320.00$87.00$20,880.00
2503.54127" RC PIPE SEWER DESIGN 3006 CLASS IVLIN FT414$49.00$20,286.00$65.10$26,951.40$61.00$25,254.00$73.40$30,387.60$55.00$22,770.00$56.00$23,184.00
2503.54118" RC PIPE SEWER DESIGN 3006 CLASS IIILIN FT839$33.00$27,687.00$37.60$31,546.40$37.00$31,043.00$37.70$31,630.30$43.00$36,077.00$33.00$27,687.00
2503.54118" RC PIPE SEWER DESIGN 3006LIN FT1,497$33.00$49,401.00$35.45$53,068.65$35.00$52,395.00$37.70$56,436.90$43.00$64,371.00$33.00$49,401.00
2503.54124" RC PIPE SEWER DESIGN 3006 CLASS IVLIN FT112$40.00$4,480.00$55.55$6,221.60$49.00$5,488.00$75.50$8,456.00$45.00$5,040.00$43.00$4,816.00
2503.54136" RC PIPE SEWER DESIGN 3006LIN FT551$62.00$34,162.00$70.15$38,652.65$76.00$41,876.00$95.40$52,565.40$70.00$38,570.00$68.50$37,743.50
2503.54121" RC PIPE SEWER DESIGN 3006 CLASS IVLIN FT481$35.00$16,835.00$44.65$21,476.65$44.00$21,164.00$56.40$27,128.40$43.00$20,683.00$38.50$18,518.50
2503.54142" RC PIPE SEWER DESIGN 3006LIN FT372$81.00$30,132.00$90.00$33,480.00$91.00$33,852.00$123.00$45,756.00$90.00$33,480.00$82.50$30,690.00
2503.54115" RC PIPE SEWER DESIGN 3006 CLASS IIILIN FT8,611$29.00$249,719.00$32.75$282,010.25$35.00$301,385.00$32.10$276,413.10$43.00$370,273.00$30.50$262,635.50
2503.54121" RC PIPE SEWER DESIGN 3006LIN FT949$35.00$33,215.00$41.00$38,909.00$40.00$37,960.00$50.30$47,734.70$43.00$40,807.00$38.50$36,536.50
2503.602CONNECT INTO EXISTING DRAINAGE STRUCTUREEACH9$500.00$4,500.00$730.00$6,570.00$900.00$8,100.00$1,790.00$16,110.00$1,000.00$9,000.00$750.00$6,750.00
2503.602CONNECT TO EXISTING SANITARY SEWEREACH2$500.00$1,000.00$1,345.00$2,690.00$850.00$1,700.00$801.00$1,602.00$800.00$1,600.00$200.00$400.00
2503.602RECONNECT SANITARY SEWER SERVICEEACH5$500.00$2,500.00$195.00$975.00$800.00$4,000.00$763.00$3,815.00$500.00$2,500.00$200.00$1,000.00
2503.602CONNECT TO EXISTING STORM SEWEREACH6$500.00$3,000.00$430.00$2,580.00$750.00$4,500.00$1,790.00$10,740.00$1,000.00$6,000.00$750.00$4,500.00
2503.6028"X4" PVC WYEEACH4$100.00$400.00$56.00$224.00$115.00$460.00$799.00$3,196.00$100.00$400.00$100.00$400.00
2503.602CONNECT TO EXISTING MANHOLES (SAN)EACH1$500.00$500.00$1,485.00$1,485.00$1,100.00$1,100.00$5,700.00$5,700.00$1,000.00$1,000.00$1,500.00$1,500.00
2503.6038" HDPE PIPE SEWERLIN FT52$40.00$2,080.00$20.00$1,040.00$30.00$1,560.00$29.70$1,544.40$50.00$2,600.00$16.00$832.00
2503.6034" PVC SANITARY SERVICE PIPELIN FT188$30.00$5,640.00$25.00$4,700.00$34.00$6,392.00$29.20$5,489.60$60.00$11,280.00$20.00$3,760.00
2503.6044" INSULATIONSQ YD16$50.00$800.00$28.00$448.00$32.00$512.00$21.30$340.80$22.00$352.00$30.00$480.00
2504.601TEMPORARY WATER SERVICELUMP SUM1$15,000.00$15,000.00$24,000.00$24,000.00$7,800.00$7,800.00$4,530.00$4,530.00$20,000.00$20,000.00$3,000.00$3,000.00
2504.602CONNECT TO EXISTING WATERMAIN (SPEC)EACH1$2,000.00$2,000.00$2,145.00$2,145.00$1,000.00$1,000.00$5,780.00$5,780.00$2,000.00$2,000.00$2,000.00$2,000.00
2504.602ADJUST GATE VALVEEACH11$250.00$2,750.00$750.00$8,250.00$170.00$1,870.00$226.00$2,486.00$500.00$5,500.00$100.00$1,100.00
2504.6021" CORPORATION STOPEACH6$200.00$1,200.00$175.00$1,050.00$500.00$3,000.00$120.00$720.00$400.00$2,400.00$150.00$900.00
2504.602CONNECT TO EXISTING WATER MAINEACH15$1,000.00$15,000.00$950.00$14,250.00$1,000.00$15,000.00$1,110.00$16,650.00$1,000.00$15,000.00$1,500.00$22,500.00
2504.6021" CURB STOP & BOXEACH6$250.00$1,500.00$170.00$1,020.00$120.00$720.00$426.00$2,556.00$1,000.00$6,000.00$150.00$900.00
2504.60212" GATE VALVE AND BOXEACH8$2,500.00$20,000.00$2,935.00$23,480.00$2,500.00$20,000.00$5,280.00$42,240.00$3,000.00$24,000.00$2,400.00$19,200.00
2504.60216" GATE VALVE AND BOXEACH3$7,000.00$21,000.00$6,600.00$19,800.00$7,000.00$21,000.00$7,410.00$22,230.00$8,000.00$24,000.00$6,500.00$19,500.00
2504.602RECONNECT WATER SERVICEEACH6$500.00$3,000.00$110.00$660.00$700.00$4,200.00$636.00$3,816.00$500.00$3,000.00$200.00$1,200.00
2504.602INSTALL HYDRANTEACH7$3,000.00$21,000.00$3,000.00$21,000.00$3,200.00$22,400.00$3,470.00$24,290.00$2,500.00$17,500.00$2,700.00$18,900.00
2504.6026" GATE VALVE AND BOXEACH16$1,250.00$20,000.00$1,245.00$19,920.00$1,100.00$17,600.00$1,830.00$29,280.00$1,500.00$24,000.00$1,100.00$17,600.00
2504.60210" MJ ADAPTEREACH2$500.00$1,000.00$615.00$1,230.00$250.00$500.00$3,260.00$6,520.00$1,000.00$2,000.00$400.00$800.00
2504.6028" GATE VALVE AND BOXEACH5$1,600.00$8,000.00$1,590.00$7,950.00$1,450.00$7,250.00$2,450.00$12,250.00$2,000.00$10,000.00$1,400.00$7,000.00
2504.6026"X6" WET TAPEACH1$4,000.00$4,000.00$3,200.00$3,200.00$3,900.00$3,900.00$2,360.00$2,360.00$3,000.00$3,000.00$2,500.00$2,500.00
2504.60314 INCH HDPE WM (DIRECTIONALLY DRILLED)LIN FT800$65.00$52,000.00$61.50$49,200.00$53.00$42,400.00$66.70$53,360.00$65.00$52,000.00$70.00$56,000.00
2504.6031" TYPE K COPPER PIPELIN FT157$20.00$3,140.00$31.00$4,867.00$24.00$3,768.00$52.40$8,226.80$30.00$4,710.00$20.00$3,140.00
2504.60316" PVC WATERMAINLIN FT600$35.00$21,000.00$29.25$17,550.00$36.00$21,600.00$45.20$27,120.00$65.00$39,000.00$30.00$18,000.00
2504.603INSPECTION HOLELIN FT25$50.00$1,250.00$235.00$5,875.00$82.00$2,050.00$47.30$1,182.50$30.00$750.00$100.00$2,500.00
2504.6038" PVC WATERMAINLIN FT1,358$25.00$33,950.00$19.50$26,481.00$26.00$35,308.00$31.80$43,184.40$47.00$63,826.00$20.00$27,160.00
2504.6036" PVC WATERMAINLIN FT392$40.00$15,680.00$18.50$7,252.00$24.00$9,408.00$34.00$13,328.00$45.00$17,640.00$18.00$7,056.00
2504.60310" WATERMAIN HDPE(DIRECTIONALY DRILLED)LIN FT755$45.00$33,975.00$49.30$37,221.50$44.00$33,220.00$52.60$39,713.00$40.00$30,200.00$45.00$33,975.00
2504.60312" PVC WATERMAINLIN FT1,025$31.00$31,775.00$25.00$25,625.00$32.00$32,800.00$44.90$46,022.50$53.00$54,325.00$25.00$25,625.00
2504.604WATERMAIN INSULATIONSQ YD12$50.00$600.00$35.00$420.00$38.00$456.00$16.90$202.80$22.00$264.00$30.00$360.00
2504.608WATERMAIN FITTINGSPOUND8,535$6.00$51,210.00$7.10$60,598.50$3.00$25,605.00$6.20$52,917.00$5.00$42,675.00$4.00$34,140.00
2506.501CONSTRUCT DRAINAGE STRUCTURE DESIGN HLIN FT3$200.00$600.00$330.00$990.00$400.00$1,200.00$535.00$1,605.00$200.00$600.00$179.00$537.00
2506.501CONSTRUCT DRAINAGE STRUCTURE DESIGN 60-4020LIN FT49.4$350.00$17,290.00$343.00$16,944.20$300.00$14,820.00$333.00$16,450.20$400.00$19,760.00$327.00$16,153.80
2506.501CONSTRUCT DRAINAGE STRUCTURE DESIGN 78-4020LIN FT36.5$650.00$23,725.00$605.00$22,082.50$570.00$20,805.00$918.00$33,507.00$800.00$29,200.00$586.00$21,389.00
2506.501CONSTRUCT DRAINAGE STRUCTURE DESIGN 72-4020LIN FT9.6$450.00$4,320.00$434.00$4,166.40$390.00$3,744.00$406.00$3,897.60$450.00$4,320.00$418.00$4,012.80
2506.501CONSTRUCT DRAINAGE STRUCTURE DESIGN GLIN FT372.1$225.00$83,722.50$287.00$106,792.70$330.00$122,793.00$339.00$126,141.90$200.00$74,420.00$215.00$80,001.50
2506.501CONSTRUCT DRAINAGE STRUCTURE DESIGN 54-4020LIN FT53.8$350.00$18,830.00$412.00$22,165.60$340.00$18,292.00$384.00$20,659.20$400.00$21,520.00$302.00$16,247.60
2506.501CONSTRUCT DRAINAGE STRUCTURE DESIGN SDLIN FT22.6$225.00$5,085.00$407.00$9,198.20$420.00$9,492.00$467.00$10,554.20$300.00$6,780.00$271.00$6,124.60
2506.501CONSTRUCT DRAINAGE STRUCTURE DESIGN 66-4020LIN FT73.2$450.00$32,940.00$439.00$32,134.80$380.00$27,816.00$423.00$30,963.60$450.00$32,940.00$408.00$29,865.60
2506.501CONSTRUCT DRAINAGE STRUCTURE DESIGN FLIN FT503.1$225.00$113,197.50$248.00$124,768.80$250.00$125,775.00$262.00$131,812.20$200.00$100,620.00$198.00$99,613.80
2506.502CONSTRUCT DRAINAGE STRUCTURE DESIGN SPECIAL 1EACH1$40,000.00$40,000.00$6,400.00$6,400.00$43,000.00$43,000.00$52,500.00$52,500.00$80,000.00$80,000.00$67,000.00$67,000.00
2506.502CONST DRAINAGE STRUCTURE DESIGN SPEC 10EACH1$35,000.00$35,000.00$52,500.00$52,500.00$34,800.00$34,800.00$35,500.00$35,500.00$55,000.00$55,000.00$44,000.00$44,000.00
2506.502CONSTRUCT DRAINAGE STRUCTURE DESIGN SPECIAL 6EACH1$5,200.00$5,200.00$7,357.00$7,357.00$5,800.00$5,800.00$3,920.00$3,920.00$8,000.00$8,000.00$3,100.00$3,100.00
2506.502CONST DRAINAGE STRUCTURE DESIGN SPEC 13EACH1$30,000.00$30,000.00$20,650.00$20,650.00$4,200.00$4,200.00$13,800.00$13,800.00$22,000.00$22,000.00$16,500.00$16,500.00
2506.502CONSTRUCT DRAINAGE STRUCTURE DESIGN SPECIAL 4EACH1$3,600.00$3,600.00$8,465.00$8,465.00$5,800.00$5,800.00$4,230.00$4,230.00$8,000.00$8,000.00$2,925.00$2,925.00
2506.502CONSTRUCT DRAINAGE STRUCTURE DESIGN SPECIAL 2EACH1$23,000.00$23,000.00$40,500.00$40,500.00$25,000.00$25,000.00$29,600.00$29,600.00$50,000.00$50,000.00$45,000.00$45,000.00
2506.502CONST DRAINAGE STRUCTURE DESIGN SPEC 11EACH1$22,500.00$22,500.00$51,300.00$51,300.00$24,500.00$24,500.00$25,200.00$25,200.00$30,000.00$30,000.00$31,000.00$31,000.00
2506.502CONSTRUCT DRAINAGE STRUCTURE DESIGN SPECIAL 7EACH1$5,400.00$5,400.00$8,700.00$8,700.00$5,800.00$5,800.00$3,920.00$3,920.00$8,000.00$8,000.00$4,022.00$4,022.00
2506.502CONSTRUCT DRAINAGE STRUCTURE DESIGN SPECIAL 5EACH1$3,500.00$3,500.00$8,465.00$8,465.00$5,800.00$5,800.00$4,240.00$4,240.00$8,000.00$8,000.00$2,725.00$2,725.00
2506.502CONSTRUCT DRAINAGE STRUCTURE DESIGN SPECIAL 3EACH1$30,000.00$30,000.00$33,200.00$33,200.00$32,000.00$32,000.00$37,400.00$37,400.00$50,000.00$50,000.00$34,000.00$34,000.00
2506.502CONST DRAINAGE STRUCTURE DESIGN SPEC 14EACH1$325,000.00$325,000.00$331,000.00$331,000.00$380,000.00$380,000.00$450,500.00$450,500.00$250,000.00$250,000.00$125,000.00$125,000.00
2506.502CONSTRUCT DRAINAGE STRUCTURE DESIGN SPECIAL 8EACH1$4,700.00$4,700.00$8,205.00$8,205.00$5,800.00$5,800.00$4,250.00$4,250.00$8,000.00$8,000.00$2,700.00$2,700.00
2506.502CONST DRAINAGE STRUCTURE DESIGN SPEC 9EACH1$14,000.00$14,000.00$17,000.00$17,000.00$14,800.00$14,800.00$17,300.00$17,300.00$30,000.00$30,000.00$14,500.00$14,500.00
2506.502CONST DRAINAGE STRUCTURE DESIGN SPEC 12EACH1$25,000.00$25,000.00$48,500.00$48,500.00$24,500.00$24,500.00$24,700.00$24,700.00$35,000.00$35,000.00$30,000.00$30,000.00
2506.503RECONSTRUCT DRAINAGE STRUCTURELIN FT1$500.00$500.00$485.00$485.00$400.00$400.00$1,400.00$1,400.00$600.00$600.00$500.00$500.00
2506.516CASTING ASSEMBLYEACH202$650.00$131,300.00$385.00$77,770.00$480.00$96,960.00$1,010.00$204,020.00$600.00$121,200.00$655.00$132,310.00
2506.522ADJUST FRAME & RING CASTINGEACH14$350.00$4,900.00$385.00$5,390.00$170.00$2,380.00$396.00$5,544.00$400.00$5,600.00$500.00$7,000.00
2506.602INSTALL MANHOLEEACH5$3,100.00$15,500.00$2,920.00$14,600.00$2,300.00$11,500.00$4,280.00$21,400.00$1,500.00$7,500.00$2,400.00$12,000.00
2506.602ADJUST DRAINAGE STRUCTUREEACH5$250.00$1,250.00$170.00$850.00$400.00$2,000.00$289.00$1,445.00$750.00$3,750.00$300.00$1,500.00
2506.603RECONSTRUCT SANITARY MANHOLESLIN FT23.5$250.00$5,875.00$301.50$7,085.25$190.00$4,465.00$791.00$18,588.50$300.00$7,050.00$300.00$7,050.00
2511.501RANDOM RIPRAP CLASS IIICU YD146$100.00$14,600.00$106.00$15,476.00$72.00$10,512.00$89.30$13,037.80$100.00$14,600.00$70.00$10,220.00
2521.5016" CONCRETE WALKSQ FT6,367$7.67$48,834.89$7.65$48,707.55$6.50$41,385.50$4.70$29,924.90$4.60$29,288.20$6.05$38,520.35
2521.5014" CONCRETE WALK SPECIALSQ FT16,988$3.40$57,759.20$4.55$77,295.40$3.50$59,458.00$3.85$65,403.80$4.00$67,952.00$3.55$60,307.40
2521.5014" CONCRETE WALKSQ FT16,429$3.10$50,929.90$3.85$63,251.65$3.00$49,287.00$4.05$66,537.45$4.00$65,716.00$2.90$47,644.10
2521.5114" BITUMINOUS WALKSQ FT101,193$1.50$151,789.50$2.40$242,863.20$1.60$161,908.80$1.55$156,849.15$1.50$151,789.50$1.50$151,789.50
2521.5114" BITUMINOUS BOULEVARDSQ FT5,615$3.00$16,845.00$4.70$26,390.50$3.20$17,968.00$3.05$17,125.75$3.00$16,845.00$3.00$16,845.00
2531.501CONCRETE CURB & GUTTER DESIGN B612LIN FT238$19.50$4,641.00$20.00$4,760.00$20.25$4,819.50$18.60$4,426.80$20.00$4,760.00$19.00$4,522.00
2531.501CONCRETE CURB & GUTTER DESIGN B424LIN FT12,231$15.30$187,134.30$13.40$163,895.40$13.70$167,564.70$14.40$176,126.40$14.00$171,234.00$12.75$155,945.25
2531.501CONCRETE CURB & GUTTER DESIGN D412LIN FT3,649$14.20$51,815.80$9.90$36,125.10$10.00$36,490.00$12.00$43,788.00$12.00$43,788.00$9.45$34,483.05
2531.501CONCRETE CURB & GUTTER DESIGN B624LIN FT11,748$15.30$179,744.40$14.35$168,583.80$14.70$172,695.60$16.00$187,968.00$16.00$187,968.00$13.65$160,360.20
2531.503CONCRETE MEDIANSQ YD2,679$66.00$176,814.00$26.00$69,654.00$26.50$70,993.50$28.20$75,547.80$27.00$72,333.00$24.75$66,305.25
2531.503CONCRETE MEDIAN (NOSE)SQ YD88$54.00$4,752.00$61.45$5,407.60$63.00$5,544.00$70.90$6,239.20$70.00$6,160.00$58.50$5,148.00
2531.5076" CONCRETE DRIVEWAY PAVEMENTSQ YD231$48.00$11,088.00$49.50$11,434.50$45.00$10,395.00$49.80$11,503.80$50.00$11,550.00$41.85$9,667.35
2533.507PORTABLE PRECAST CONCRETE BARRIER DES 8337LIN FT4,000$10.00$40,000.00$11.00$44,000.00$10.75$43,000.00$10.10$40,400.00$12.00$48,000.00$9.25$37,000.00
2533.508RELOCATE PORT PRECAST CONC BAR DES 8337LIN FT2,000$2.00$4,000.00$3.15$6,300.00$3.25$6,500.00$3.05$6,100.00$3.00$6,000.00$2.50$5,000.00
2540.602MAIL BOX SUPPORTEACH1$200.00$200.00$130.00$130.00$130.00$130.00$128.00$128.00$150.00$150.00$150.00$150.00
2540.602MAIL BOX SUPPORT (MULTIPLE)EACH1$200.00$200.00$370.00$370.00$210.00$210.00$358.00$358.00$250.00$250.00$250.00$250.00
2554.602IMPACT ATTENUATOR BARRELSEACH72$250.00$18,000.00$0.01$0.72$180.00$12,960.00$0.01$0.72$175.00$12,600.00$10.00$720.00
2554.615RELOCATE IMPACT ATTENUATORAMBY12$500.00$6,000.00$465.00$5,580.00$430.00$5,160.00$450.00$5,400.00$400.00$4,800.00$10.00$120.00
2554.615IMPACT ATTENUATORAMBY24$2,500.00$60,000.00$0.02$0.48$1,720.00$41,280.00$0.01$0.24$1,600.00$38,400.00$10.00$240.00
2557.501WIRE FENCE DESIGN S-1 VINYL COATEDLIN FT70$29.00$2,030.00$131.00$9,170.00$31.00$2,170.00$29.30$2,051.00$29.00$2,030.00$29.00$2,030.00
2557.501WIRE FENCE DESIGN S-2 VINYL COATEDLIN FT4,085$22.00$89,870.00$46.20$188,727.00$24.00$98,040.00$22.30$91,095.50$22.00$89,870.00$22.00$89,870.00
2557.603WOODEN FENCELIN FT282$48.00$13,536.00$100.00$28,200.00$51.00$14,382.00$48.60$13,705.20$48.00$13,536.00$48.00$13,536.00
2557.603TEMPORARY FENCE DESIGN SPECIALLIN FT1,060$6.00$6,360.00$18.00$19,080.00$6.00$6,360.00$6.05$6,413.00$6.00$6,360.00$6.00$6,360.00
2563.601TRAFFIC CONTROL AREA 4LUMP SUM1$40,000.00$40,000.00$40,000.00$40,000.00$45,300.00$45,300.00$38,100.00$38,100.00$30,000.00$30,000.00$50,000.00$50,000.00
2563.601TRAFFIC CONTROL AREA 2LUMP SUM1$40,000.00$40,000.00$90,000.00$90,000.00$48,400.00$48,400.00$87,100.00$87,100.00$60,000.00$60,000.00$50,000.00$50,000.00
2563.601TRAFFIC CONTROL AREA 3LUMP SUM1$40,000.00$40,000.00$45,000.00$45,000.00$42,000.00$42,000.00$43,400.00$43,400.00$45,000.00$45,000.00$50,000.00$50,000.00
2563.601TRAFFIC CONTROL AREA 1LUMP SUM1$40,000.00$40,000.00$121,000.00$121,000.00$27,300.00$27,300.00$114,900.00$114,900.00$50,000.00$50,000.00$74,000.00$74,000.00
2563.601TRAFFIC CONTROL AREA 5LUMP SUM1$40,000.00$40,000.00$38,000.00$38,000.00$77,200.00$77,200.00$36,000.00$36,000.00$25,000.00$25,000.00$25,000.00$25,000.00
2563.602RAISED PAVEMENT MARKER TEMPORARYEACH1,000$1.50$1,500.00$1.50$1,500.00$1.60$1,600.00$1.50$1,500.00$1.50$1,500.00$0.01$10.00
2563.602PORTABLE CONCRETE BARRIER DELINEATOREACH500$6.00$3,000.00$4.75$2,375.00$4.80$2,400.00$4.60$2,300.00$4.50$2,250.00$0.10$50.00
2563.613FLASHER TYPE B (HIGH INTENSITY)UDAY500$1.00$500.00$0.55$275.00$0.50$250.00$0.51$255.00$0.50$250.00$0.10$50.00
2563.6134'X4'SIGN WITH SUPPORTSUDAY500$1.00$500.00$2.35$1,175.00$2.00$1,000.00$2.25$1,125.00$1.75$875.00$0.10$50.00
2563.613REFLECTORIZED PLASTIC SAFETY DRUMUDAY500$1.00$500.00$1.00$500.00$0.75$375.00$0.87$435.00$0.70$350.00$0.10$50.00
2563.613PORTABLE CHANGEABLE MESSAGE SIGNUDAY600$50.00$30,000.00$0.01$6.00$54.00$32,400.00$0.01$6.00$50.00$30,000.00$1.00$600.00
2563.613TYPE III BARRICADESUDAY1,000$1.00$1,000.00$2.90$2,900.00$3.00$3,000.00$2.80$2,800.00$2.00$2,000.00$0.10$100.00
2563.618CONSTRUCTION SIGN-SPECIALSQ FT1,500$30.00$45,000.00$0.01$15.00$17.00$25,500.00$0.01$15.00$15.00$22,500.00$1.00$1,500.00
2564.531SIGN PANELS TYPE CSQ FT845$27.80$23,491.00$30.00$25,350.00$32.00$27,040.00$28.10$23,744.50$31.00$26,195.00$28.00$23,660.00
2564.536INSTALL SIGN PANELEACH32$63.00$2,016.00$95.00$3,040.00$60.00$1,920.00$91.90$2,940.80$100.00$3,200.00$85.00$2,720.00
2565.511TRAFFIC CONTROL SIGNAL SYSTEM ASIG SYS1$135,660.59$135,660.59$154,000.00$154,000.00$147,000.00$147,000.00$155,800.00$155,800.00$165,000.00$165,000.00$135,661.00$135,661.00
2565.511TRAFFIC CONTROL SIGNAL SYSTEM BSIG SYS1$141,054.51$141,054.51$182,000.00$182,000.00$152,000.00$152,000.00$184,000.00$184,000.00$165,000.00$165,000.00$141,055.00$141,055.00
2565.616TEMPORARY SIGNAL SYSTEMSYSTEM1$77,418.78$77,418.78$74,000.00$74,000.00$83,300.00$83,300.00$74,800.00$74,800.00$95,000.00$95,000.00$77,419.00$77,419.00
2571.501CONIFEROUS TREE 6' HT B&BTREE63$258.35$16,276.05$2.55$160.65$260.00$16,380.00$245.00$15,435.00$242.00$15,246.00$258.35$16,276.05
2571.502DECIDUOUS TREE 2.5" CAL B&BTREE100$307.39$30,739.00$280.00$28,000.00$275.00$27,500.00$270.00$27,000.00$267.00$26,700.00$307.39$30,739.00
2571.505DECIDUOUS SHRUB 12" HT CONTSHRUB138$40.54$5,594.52$50.00$6,900.00$50.00$6,900.00$48.60$6,706.80$48.00$6,624.00$40.54$5,594.52
2572.501TEMPORARY FENCELIN FT1,000$3.00$3,000.00$2.00$2,000.00$1.80$1,800.00$1.90$1,900.00$2.00$2,000.00$1.50$1,500.00
2573.502SILT FENCE, TYPE MACHINE SLICEDLIN FT2,602$1.54$4,007.08$2.30$5,984.60$1.80$4,683.60$1.95$5,073.90$3.00$7,806.00$1.54$4,007.08
2573.502SILT FENCE, TYPE SUPER DUTYLIN FT100$10.00$1,000.00$31.50$3,150.00$3.25$325.00$1.95$195.00$8.00$800.00$16.00$1,600.00
2573.504INLET PROTECTION SANDBAG BARRIERSQ FT200$5.00$1,000.00$5.00$1,000.00$27.00$5,400.00$2.30$460.00$3.00$600.00$30.00$6,000.00
2573.504SANDBAG BARRIERSQ FT1,000$5.00$5,000.00$3.15$3,150.00$3.00$3,000.00$3.00$3,000.00$3.00$3,000.00$6.00$6,000.00
2573.505FLOTATION SILT CURTAIN TYPE STILL WATERLIN FT1,114$10.00$11,140.00$11.00$12,254.00$13.00$14,482.00$10.70$11,919.80$10.00$11,140.00$10.00$11,140.00
2573.512TEMPORARY DITCH CHECK TYPE 3LIN FT44$3.10$136.40$4.15$182.60$5.40$237.60$4.05$178.20$12.00$528.00$3.10$136.40
2573.520SEDIMENT REMOVAL BACKHOEHOUR100$100.00$10,000.00$382.00$38,200.00$235.00$23,500.00$154.00$15,400.00$120.00$12,000.00$140.00$14,000.00
2573.530INLET PROTECTION TYPE AEACH5$150.00$750.00$115.00$575.00$100.00$500.00$177.00$885.00$300.00$1,500.00$250.00$1,250.00
2573.530INLET PROTECTION TYPE CEACH182$150.00$27,300.00$70.00$12,740.00$65.00$11,830.00$35.30$6,424.60$200.00$36,400.00$100.00$18,200.00
2573.550EROSION CONTROL SUPERVISORLUMP SUM1$20,000.00$20,000.00$11,715.00$11,715.00$66,000.00$66,000.00$10,600.00$10,600.00$30,000.00$30,000.00$75,000.00$75,000.00
2573.602ROCK DITCH CHECKEACH1$1,000.00$1,000.00$310.00$310.00$540.00$540.00$455.00$455.00$2,000.00$2,000.00$500.00$500.00
2573.602TEMPORARY ROCK CONSTRUCTION ENTRANCEEACH1$1,000.00$1,000.00$1,100.00$1,100.00$2,080.00$2,080.00$1,500.00$1,500.00$2,000.00$2,000.00$3,500.00$3,500.00
2573.602WET SWALEEACH1$20,000.00$20,000.00$3,140.00$3,140.00$1,300.00$1,300.00$11,500.00$11,500.00$5,000.00$5,000.00$12,050.00$12,050.00
2573.603BIOROLLLIN FT4,104$2.45$10,054.80$3.50$14,364.00$3.25$13,338.00$3.30$13,543.20$2.45$10,054.80$2.45$10,054.80
2575.501SEEDINGACRE4.83$350.00$1,690.50$160.00$772.80$105.00$507.15$153.00$738.99$350.00$1,690.50$350.00$1,690.50
2575.502SEED MIXTURE 150POUND72$1.74$125.28$4.00$288.00$2.70$194.40$4.05$291.60$2.00$144.00$1.74$125.28
2575.502SEED MIXTURE 350POUND256$3.27$837.12$5.00$1,280.00$4.00$1,024.00$4.05$1,036.80$4.00$1,024.00$3.27$837.12
2575.502COMMERCIAL FERTILIZER ANALYSIS 22-5-10POUND2,182$0.50$1,091.00$0.70$1,527.40$0.50$1,091.00$0.66$1,440.12$0.50$1,091.00$0.50$1,091.00
2575.505SODDING TYPE SALT RESISTANTSQ YD31,462$2.33$73,306.46$2.50$78,655.00$2.70$84,947.40$2.45$77,081.90$2.30$72,362.60$2.33$73,306.46
2575.511MULCH MATERIAL TYPE 3TON11.82$150.00$1,773.00$250.00$2,955.00$105.00$1,241.10$235.00$2,777.70$150.00$1,773.00$150.00$1,773.00
2575.519DISK ANCHORINGACRE6.23$75.00$467.25$65.00$404.95$50.00$311.50$61.30$381.90$75.00$467.25$75.00$467.25
2575.523EROSION CONTROL BLANKETS CATEGORY 1SQ YD50$1.00$50.00$1.50$75.00$2.15$107.50$1.50$75.00$1.00$50.00$1.00$50.00
2575.523EROSION CONTROL BLANKETS CATEGORY 3SQ YD90$1.00$90.00$1.50$135.00$2.15$193.50$1.50$135.00$1.00$90.00$1.00$90.00
2575.550COMPOST, GRADE 2CU YD30$73.07$2,192.10$136.00$4,080.00$32.00$960.00$80.00$2,400.00$200.00$6,000.00$183.00$5,490.00
2575.570RAPID STABILIZATION METHOD 1ACRE1.8$650.00$1,170.00$660.00$1,188.00$860.00$1,548.00$638.00$1,148.40$650.00$1,170.00$650.00$1,170.00
2575.571RAPID STABILIZATION METHOD 3M GALLONS1$300.00$300.00$415.00$415.00$835.00$835.00$404.00$404.00$300.00$300.00$300.00$300.00
2575.60224" TEMPORARY STANDPIPEEACH1$500.00$500.00$680.00$680.00$400.00$400.00$1,020.00$1,020.00$600.00$600.00$617.00$617.00
2575.60218" TEMPORARY STANDPIPEEACH3$500.00$1,500.00$570.00$1,710.00$800.00$2,400.00$718.00$2,154.00$600.00$1,800.00$517.00$1,551.00
2575.60215" TEMPORARY STANDPIPEEACH1$500.00$500.00$515.00$515.00$900.00$900.00$878.00$878.00$600.00$600.00$467.00$467.00
2575.60221" TEMPORARY STANDPIPEEACH1$500.00$500.00$625.00$625.00$400.00$400.00$1,010.00$1,010.00$600.00$600.00$567.00$567.00
2581.501REMOVABLE PREFORMED PLASTIC MARKINGLIN FT4,000$1.20$4,800.00$1.05$4,200.00$1.10$4,400.00$1.00$4,000.00$1.00$4,000.00$0.90$3,600.00
2582.501PAVT MSSG (LT ARROW) POLY PREFEACH30$335.00$10,050.00$225.00$6,750.00$65.00$1,950.00$215.00$6,450.00$213.00$6,390.00$213.00$6,390.00
2582.501PAVT MSSG (RT ARROW) POLY PREFEACH16$335.00$5,360.00$225.00$3,600.00$229.00$3,664.00$215.00$3,440.00$213.00$3,408.00$213.00$3,408.00
2582.501PAVT MSSG (LT ARROW) PAINTEACH5$93.80$469.00$65.00$325.00$105.00$525.00$61.90$309.50$100.00$500.00$100.00$500.00
2582.501PAVT MSSG (RT ARROW) PAINTEACH5$93.80$469.00$65.00$325.00$105.00$525.00$61.90$309.50$100.00$500.00$100.00$500.00
2582.5024" BROKEN LINE WHITE-PAINTLIN FT500$1.35$675.00$1.20$600.00$0.30$150.00$1.10$550.00$1.00$500.00$0.30$150.00
2582.5024" DOUBLE SOLID LINE YELLOW-PAINTLIN FT2,000$2.66$5,320.00$2.30$4,600.00$0.70$1,400.00$2.20$4,400.00$0.70$1,400.00$0.70$1,400.00
2582.5024" DOTTED LINE WHITE-PAINTLIN FT50$1.35$67.50$1.20$60.00$0.50$25.00$1.10$55.00$1.00$50.00$0.50$25.00
2582.50224"SOLID LINE YELLOW-PAINTLIN FT100$12.76$1,276.00$10.00$1,000.00$4.00$400.00$9.90$990.00$4.00$400.00$4.00$400.00
2582.50224" SOLID LINE YELLOW-POLY PREF (GR IN)LIN FT510$27.50$14,025.00$21.00$10,710.00$21.00$10,710.00$20.10$10,251.00$20.00$10,200.00$19.87$10,133.70
2582.5024" DOTTED LINE WHITE EPOXYLIN FT129$0.61$78.69$0.55$70.95$0.50$64.50$0.50$64.50$1.30$167.70$0.50$64.50
2582.5024" BROKEN LINE WHITE-EPOXYLIN FT3,370$0.61$2,055.70$0.55$1,853.50$0.50$1,685.00$0.50$1,685.00$0.30$1,011.00$0.50$1,685.00
2582.5024" SOLID LINE WHITE-PAINTLIN FT1,000$1.35$1,350.00$1.20$1,200.00$0.30$300.00$1.10$1,100.00$1.00$1,000.00$0.30$300.00
2582.5024" SOLID LINE WHITE-EPOXYLIN FT6,311$0.61$3,849.71$0.55$3,471.05$0.50$3,155.50$0.50$3,155.50$0.30$1,893.30$0.50$3,155.50
2582.5024" DB SOLID LINE YELLOW-POLY PREF(GR IN)LIN FT5,726$8.50$48,671.00$8.80$50,388.80$9.00$51,534.00$8.50$48,671.00$8.50$48,671.00$8.39$48,041.14
2582.503CROSSWALK MARKING-POLY PREFORMSQ FT2,034$12.95$26,340.30$8.40$17,085.60$8.00$16,272.00$8.05$16,373.70$8.00$16,272.00$7.95$16,170.30
2582.503CROSSWALK MARKING-PAINTSQ FT200$6.70$1,340.00$4.60$920.00$2.00$400.00$4.45$890.00$2.00$400.00$2.00$400.00
 Totals for project 2951600 $14,253,578.06 $14,904,565.75 $15,251,630.52 $16,109,360.35 $16,323,226.19 $16,452,286.00
 
Contract Total:$14,253,578.06$14,904,565.75$15,251,630.52$16,109,360.35$16,323,226.19$16,452,286.00