2155300 - Span Wire Signal ReplacementsGranite Ledge Electrical Contractors Inc Egan Company Concrete Idea Inc Killmer Electric Co. Inc. Premier Electrical Corporation 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLUMP SUM1$11,613.00$11,613.00$27,000.00$27,000.00$85,000.00$85,000.00$30,000.00$30,000.00$26,411.00$26,411.00
2101.501CLEARINGACRE0.05$44,880.00$2,244.00$42,000.00$2,100.00$2,000.00$100.00$42,800.00$2,140.00$46,500.00$2,325.00
2101.506GRUBBINGACRE0.05$16,830.00$841.50$15,750.00$787.50$2,000.00$100.00$16,050.00$802.50$17,450.00$872.50
2102.501PAVEMENT MARKING REMOVALSQ FT1,730$2.81$4,861.30$2.63$4,549.90$2.50$4,325.00$2.70$4,671.00$3.50$6,055.00
2102.502PAVEMENT MARKING REMOVALLIN FT125$1.12$140.00$1.05$131.25$1.00$125.00$1.10$137.50$2.40$300.00
2104.501REMOVE CURB & GUTTERLIN FT220$16.83$3,702.60$15.75$3,465.00$5.00$1,100.00$16.05$3,531.00$17.50$3,850.00
2104.503REMOVE BITUMINOUS WALKSQ FT3,130$2.24$7,011.20$2.10$6,573.00$2.50$7,825.00$2.15$6,729.50$2.40$7,512.00
2104.503REMOVE CONCRETE WALKSQ FT1,965$3.37$6,622.05$3.10$6,091.50$2.00$3,930.00$3.20$6,288.00$3.50$6,877.50
2104.505REMOVE BITUMINOUS PAVEMENTSQ YD315$30.29$9,541.35$28.50$8,977.50$27.00$8,505.00$28.90$9,103.50$31.50$9,922.50
2104.509REMOVE SIGNAL SYSTEM AEACH1$6,225.00$6,225.00$6,500.00$6,500.00$7,125.00$7,125.00$7,750.00$7,750.00$7,550.00$7,550.00
2104.509REMOVE SIGNAL SYSTEM BEACH1$6,225.00$6,225.00$6,500.00$6,500.00$7,125.00$7,125.00$7,750.00$7,750.00$7,550.00$7,550.00
2104.513SAWING BIT PAVEMENT (FULL DEPTH)LIN FT750$3.37$2,527.50$3.15$2,362.50$7.00$5,250.00$3.20$2,400.00$3.50$2,625.00
2104.523SALVAGE SIGN PANEL TYPE SPECIALEACH1$56.10$56.10$52.00$52.00$75.00$75.00$50.00$50.00$58.25$58.25
2104.523SALVAGE SIGN TYPE SPECIALEACH2$56.10$112.20$27.00$54.00$75.00$150.00$50.00$100.00$58.25$116.50
2104.523SALVAGE SIGN TYPE CEACH1$56.10$56.10$53.00$53.00$75.00$75.00$50.00$50.00$58.25$58.25
2105.501COMMON EXCAVATIONCU YD140$50.00$7,000.00$52.00$7,280.00$25.00$3,500.00$50.00$7,000.00$58.25$8,155.00
2123.610STREET SWEEPER (WITH PICKUP BROOM)HOUR20$2.24$44.80$1.05$21.00$5.00$100.00$1.10$22.00$1.25$25.00
2211.503AGGREGATE BASE (CV) CLASS 5CU YD210$61.71$12,959.10$57.00$11,970.00$25.00$5,250.00$58.85$12,358.50$65.00$13,650.00
2231.501BITUMINOUS PATCHING MIXTURETON95$252.45$23,982.75$236.00$22,420.00$250.00$23,750.00$240.00$22,800.00$261.50$24,842.50
2301.602DRILL & GROUT REINF BAR (EPOXY COATED)EACH116$21.88$2,538.08$20.50$2,378.00$15.00$1,740.00$21.00$2,436.00$22.75$2,639.00
2521.5014" CONCRETE WALKSQ FT1,710$8.42$14,398.20$7.90$13,509.00$14.00$23,940.00$8.00$13,680.00$8.75$14,962.50
2521.5016" CONCRETE WALKSQ FT3,300$10.66$35,178.00$10.00$33,000.00$16.00$52,800.00$10.15$33,495.00$11.50$37,950.00
2521.5113" BITUMINOUS WALKSQ FT740$5.61$4,151.40$5.25$3,885.00$9.00$6,660.00$5.35$3,959.00$6.00$4,440.00
2531.501CONCRETE CURB & GUTTER DESIGN B618LIN FT140$42.08$5,891.20$39.40$5,516.00$32.00$4,480.00$40.15$5,621.00$43.75$6,125.00
2531.501CONCRETE CURB & GUTTER DESIGN B624LIN FT390$44.32$17,284.80$41.50$16,185.00$32.00$12,480.00$42.25$16,477.50$46.00$17,940.00
2531.618TRUNCATED DOMESSQ FT392$44.88$17,592.96$41.50$16,268.00$40.00$15,680.00$42.25$16,562.00$46.00$18,032.00
2563.601TRAFFIC CONTROLLUMP SUM1$15,127.01$15,127.01$10,500.00$10,500.00$10,000.00$10,000.00$14,615.00$14,615.00$11,575.00$11,575.00
2564.537INSTALL SIGN TYPE CEACH1$224.40$224.40$210.00$210.00$500.00$500.00$215.00$215.00$235.00$235.00
2565.511TRAFFIC CONTROL SIGNAL SYSTEM BSIG SYS1$122,112.00$122,112.00$131,200.00$131,200.00$120,550.00$120,550.00$151,095.00$151,095.00$144,150.00$144,150.00
2565.511TRAFFIC CONTROL SIGNAL SYSTEM ASIG SYS1$136,794.00$136,794.00$144,300.00$144,300.00$134,650.00$134,650.00$171,745.00$171,745.00$160,500.00$160,500.00
2565.513EMERGENCY VEHICLE PREEMPTION SYSTEM BLUMP SUM1$5,600.00$5,600.00$9,000.00$9,000.00$8,620.00$8,620.00$8,940.00$8,940.00$8,900.00$8,900.00
2565.513EMERGENCY VEHICLE PREEMPTION SYSTEM ALUMP SUM1$6,500.00$6,500.00$10,200.00$10,200.00$11,150.00$11,150.00$8,940.00$8,940.00$11,500.00$11,500.00
2573.502SILT FENCE, TYPE MSLIN FT400$7.29$2,916.00$6.83$2,732.00$7.00$2,800.00$3.75$1,500.00$4.25$1,700.00
2573.530STORM DRAIN INLET PROTECTIONEACH16$336.00$5,376.00$94.50$1,512.00$25.00$400.00$320.00$5,120.00$350.00$5,600.00
2573.533SEDIMENT CONTROL LOG TYPE STRAWLIN FT200$5.61$1,122.00$6.83$1,366.00$6.00$1,200.00$5.35$1,070.00$6.00$1,200.00
2575.602SITE RESTORATIONEACH8$821.82$6,574.56$630.00$5,040.00$350.00$2,800.00$640.00$5,120.00$700.00$5,600.00
2582.5026" SOLID LINE EPOXY GR INLIN FT60$5.61$336.60$10.50$630.00$5.00$300.00$10.70$642.00$6.00$360.00
2582.503CROSSWALK PREF THERMO GR INSQ FT1,687$12.90$21,762.30$13.15$22,184.05$11.50$19,400.50$13.40$22,605.80$16.50$27,835.50
 Totals for project 2155300 $527,245.06 $546,503.20 $593,560.50 $607,521.80 $610,000.00
 
Contract Total:$527,245.06$546,503.20$593,560.50$607,521.80$610,000.00