2121000 - Bridge replacement in Deephaven - Vinehill Rd over HCRRA Regional TrailLunda Construction Company C S McCrossan Construction, Inc. Edward Kraemer & Sons, Inc. S.M. Hentges & Sons, Inc. Redstone Construction Company, Inc. Robert R. Schroeder Construction, Inc. LS Black Constructors 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLS1$72,675.40$72,675.40$74,500.00$74,500.00$72,000.00$72,000.00$109,500.00$109,500.00$142,500.00$142,500.00$184,362.00$184,362.00$214,500.00$214,500.00
2101.511CLEARING & GRUBBINGLS1$9,800.00$9,800.00$11,500.00$11,500.00$8,000.00$8,000.00$10,465.00$10,465.00$11,200.00$11,200.00$11,150.00$11,150.00$10,780.00$10,780.00
2102.502PAVEMENT MARKING REMOVALL F445$0.75$333.75$1.20$534.00$0.80$356.00$1.05$467.25$0.75$333.75$0.75$333.75$1.49$663.05
2104.501REMOVE GUARDRAIL-PLATE BEAML F150$7.20$1,080.00$8.40$1,260.00$7.20$1,080.00$7.70$1,155.00$7.25$1,087.50$7.20$1,080.00$3.30$495.00
2104.501REMOVE CONCRETE CURBL F184$2.80$515.20$7.40$1,361.60$2.80$515.20$3.30$607.20$7.50$1,380.00$7.40$1,361.60$3.96$728.64
2104.501REMOVE SEWER PIPE (STORM)L F166$16.00$2,656.00$14.00$2,324.00$16.00$2,656.00$7.50$1,245.00$10.75$1,784.50$10.70$1,776.20$7.92$1,314.72
2104.505REMOVE BITUMINOUS PAVEMENT (P)S Y1,052$2.13$2,240.76$5.40$5,680.80$2.20$2,314.40$5.00$5,260.00$6.00$6,312.00$5.90$6,206.80$6.82$7,174.64
2104.509REMOVE SIGN TYPE CEACH10$25.00$250.00$41.50$415.00$25.00$250.00$26.75$267.50$25.00$250.00$25.00$250.00$38.50$385.00
2104.509REMOVE CATCH BASINEACH3$590.00$1,770.00$325.00$975.00$590.00$1,770.00$185.00$555.00$505.00$1,515.00$505.00$1,515.00$305.80$917.40
2104.509REMOVE SIGN TYPE SPECIALEACH2$25.00$50.00$41.50$83.00$25.00$50.00$26.75$53.50$25.00$50.00$25.00$50.00$44.00$88.00
2104.513SAWING BIT PAVEMENT (FULL DEPTH)L F319$3.00$957.00$5.70$1,818.30$6.00$1,914.00$4.50$1,435.50$5.50$1,754.50$5.50$1,754.50$7.70$2,456.30
2104.521SALVAGE CHAIN LINK FENCEL F21$50.00$1,050.00$29.00$609.00$50.00$1,050.00$32.00$672.00$8.00$168.00$10.00$210.00$44.00$924.00
2104.523SALVAGE SIGN TYPE CEACH8$25.00$200.00$41.50$332.00$25.00$200.00$26.75$214.00$25.00$200.00$25.00$200.00$44.00$352.00
2104.523SALVAGE SIGN TYPE SPECIALEACH6$25.00$150.00$41.50$249.00$25.00$150.00$26.75$160.50$25.00$150.00$25.00$150.00$49.50$297.00
2104.601REMOVE REGULATED WASTE MATERIAL (BRIDGE)LS1$7,500.00$7,500.00$500.00$500.00$1,500.00$1,500.00$1,125.00$1,125.00$500.00$500.00$100.00$100.00$8,250.00$8,250.00
2105.501COMMON EXCAVATION (P)C Y2,647$16.86$44,628.42$19.50$51,616.50$17.00$44,999.00$15.65$41,425.55$17.50$46,322.50$17.50$46,322.50$21.01$55,613.47
2105.522SELECT GRANULAR BORROW MOD 7% (CV) (P)C Y2,420$21.20$51,304.00$32.00$77,440.00$21.20$51,304.00$25.30$61,226.00$26.50$64,130.00$26.40$63,888.00$35.64$86,248.80
2105.525TOPSOIL BORROW (LV)CU YD42$14.00$588.00$34.50$1,449.00$14.00$588.00$28.50$1,197.00$34.00$1,428.00$33.75$1,417.50$46.09$1,935.78
2105.533SALVAGED AGGREGATEC Y32$5.20$166.40$19.50$624.00$5.20$166.40$15.00$480.00$14.25$456.00$14.25$456.00$28.27$904.64
2118.501AGGREGATE SURFACING CLASS 5TON10$14.00$140.00$76.00$760.00$14.00$140.00$22.35$223.50$33.00$330.00$32.80$328.00$45.54$455.40
2118.501AGGREGATE SURFACING CLASS SPECIALTON30$15.40$462.00$54.00$1,620.00$15.40$462.00$26.60$798.00$33.50$1,005.00$33.40$1,002.00$47.52$1,425.60
2211.503AGGREGATE BASE (CV) CLASS 5 (P)C Y253$27.46$6,947.38$57.00$14,421.00$27.50$6,957.50$41.00$10,373.00$48.50$12,270.50$48.30$12,219.90$50.05$12,662.65
2301.551BRIDGE APPROACH PANELEACH2$5,000.00$10,000.00$23,000.00$46,000.00$30,000.00$60,000.00$32,200.00$64,400.00$22,000.00$44,000.00$29,000.00$58,000.00$26,510.00$53,020.00
2357.502BITUMINOUS MATERIAL FOR TACK COAT (P)GAL77$4.00$308.00$6.40$492.80$4.00$308.00$4.25$327.25$11.25$866.25$4.00$308.00$12.34$950.18
2360.501TYPE SP 12.5 WEARING COURSE MIX (3,C)TON175$92.93$16,262.75$87.00$15,225.00$93.00$16,275.00$99.00$17,325.00$106.00$18,550.00$92.93$16,262.75$126.50$22,137.50
2360.502TYPE SP 12.5 NON WEAR COURSE MIX (3,B)TON117$89.93$10,521.81$78.50$9,184.50$90.00$10,530.00$95.80$11,208.60$99.00$11,583.00$89.93$10,521.81$118.80$13,899.60
2360.505TYPE SP 12.5 BIT MIXTURE FOR PATCHINGTON10$175.00$1,750.00$185.00$1,850.00$175.00$1,750.00$186.50$1,865.00$255.00$2,550.00$175.00$1,750.00$280.50$2,805.00
2401.501STRUCTURAL CONCRETE (1A43) (P)C Y188$600.00$112,800.00$410.00$77,080.00$540.00$101,520.00$544.00$102,272.00$370.00$69,560.00$300.00$56,400.00$467.50$87,890.00
2401.501STRUCTURAL CONCRETE (3Y43) (P)C Y250$800.00$200,000.00$525.00$131,250.00$540.00$135,000.00$755.00$188,750.00$675.00$168,750.00$625.00$156,250.00$671.00$167,750.00
2401.512BRIDGE SLAB CONCRETE (3Y36) (P)S F5,539$12.00$66,468.00$24.00$132,936.00$23.50$130,166.50$21.50$119,088.50$20.00$110,780.00$22.00$121,858.00$27.50$152,322.50
2401.513TYPE F (TL-4) RAILING CONCRETE (3Y46) (P)L F109$82.00$8,938.00$80.00$8,720.00$80.00$8,720.00$150.00$16,350.00$96.00$10,464.00$85.00$9,265.00$148.50$16,186.50
2401.513TYPE P-1 (TL-2) RAILING CONCRETE (3Y46) (P)L F149$82.00$12,218.00$80.00$11,920.00$90.00$13,410.00$140.50$20,934.50$100.00$14,900.00$110.00$16,390.00$159.50$23,765.50
2401.515SIDEWALK CONCRETE (3Y36) (P)S F783$23.00$18,009.00$15.00$11,745.00$12.00$9,396.00$6.60$5,167.80$12.00$9,396.00$14.00$10,962.00$8.53$6,678.99
2401.541REINFORCEMENT BARS (STAINLESS STEEL)LB580$3.50$2,030.00$4.20$2,436.00$5.00$2,900.00$4.10$2,378.00$4.97$2,882.60$4.50$2,610.00$3.41$1,977.80
2401.541REINFORCEMENT BARS (EPOXY COATED) (P)LB70,220$1.10$77,242.00$1.20$84,264.00$1.20$84,264.00$1.15$80,753.00$1.06$74,433.20$1.35$94,797.00$1.41$99,010.20
2401.541REINFORCEMENT BARS (P)LB15,260$1.00$15,260.00$1.10$16,786.00$1.10$16,786.00$1.10$16,786.00$0.87$13,276.20$1.25$19,075.00$1.27$19,380.20
2401.601SLOPE PREPARATIONLS1$2,800.00$2,800.00$2,000.00$2,000.00$8,800.00$8,800.00$5,900.00$5,900.00$6,000.00$6,000.00$5,950.00$5,950.00$11,741.40$11,741.40
2401.601STRUCTURE EXCAVATIONLS1$31,200.00$31,200.00$30,000.00$30,000.00$34,500.00$34,500.00$44,600.00$44,600.00$80,000.00$80,000.00$56,000.00$56,000.00$87,442.30$87,442.30
2401.618BRIDGE DECK PLANING (P)S F6,402$0.95$6,081.90$1.20$7,682.40$1.00$6,402.00$1.00$6,402.00$0.95$6,081.90$1.00$6,402.00$1.93$12,355.86
2402.595BEARING ASSEMBLYEACH12$1,500.00$18,000.00$950.00$11,400.00$1,100.00$13,200.00$780.00$9,360.00$929.00$11,148.00$850.00$10,200.00$715.00$8,580.00
2402.603METAL RAILING FOR BIKEWAYS (DESIGN M-1) (P)L F145$80.00$11,600.00$130.00$18,850.00$115.00$16,675.00$94.00$13,630.00$80.00$11,600.00$115.00$16,675.00$148.50$21,532.50
2404.501CONCRETE WEARING COURSE (3U17A) (P)S F6,944$2.00$13,888.00$8.00$55,552.00$7.40$51,385.60$7.90$54,857.60$7.50$52,080.00$4.00$27,776.00$11.00$76,384.00
2405.502PRESTRESSED CONCRETE BEAMS MN45 (P)L F638$250.00$159,500.00$195.00$124,410.00$205.00$130,790.00$174.00$111,012.00$204.00$130,152.00$225.00$143,550.00$202.40$129,131.20
2405.511DIAPHRAGMS FOR TYPE MN45 PREST BEAMSL F110$50.00$5,500.00$60.00$6,600.00$65.00$7,150.00$44.50$4,895.00$44.00$4,840.00$75.00$8,250.00$138.60$15,246.00
2442.501REMOVE EXISTING BRIDGELS1$130,000.00$130,000.00$53,000.00$53,000.00$67,800.00$67,800.00$46,650.00$46,650.00$100,000.00$100,000.00$80,000.00$80,000.00$71,500.00$71,500.00
2452.507C-I-P CONCRETE PILING DELIVERED 12"L F3,230$40.00$129,200.00$42.00$135,660.00$43.00$138,890.00$38.10$123,063.00$27.00$87,210.00$23.50$75,905.00$33.00$106,590.00
2452.508C-I-P CONCRETE PILING DRIVEN 12"L F3,230$1.00$3,230.00$1.00$3,230.00$1.00$3,230.00$3.55$11,466.50$1.00$3,230.00$4.00$12,920.00$7.70$24,871.00
2452.519C-I-P CONC TEST PILE 75 FT LONG 12"EACH2$5,000.00$10,000.00$4,200.00$8,400.00$6,000.00$12,000.00$3,850.00$7,700.00$9,000.00$18,000.00$7,500.00$15,000.00$9,900.00$19,800.00
2452.519C-I-P CONC TEST PILE 85 FT LONG 12"EACH2$6,000.00$12,000.00$4,500.00$9,000.00$6,500.00$13,000.00$4,390.00$8,780.00$10,000.00$20,000.00$8,500.00$17,000.00$10,560.00$21,120.00
2452.527PILE REDRIVINGEACH50$250.00$12,500.00$480.00$24,000.00$100.00$5,000.00$175.00$8,750.00$300.00$15,000.00$125.00$6,250.00$880.00$44,000.00
2452.602PILE POINTS 12"EACH50$250.00$12,500.00$405.00$20,250.00$220.00$11,000.00$240.00$12,000.00$277.00$13,850.00$165.00$8,250.00$247.50$12,375.00
2501.51512" RC PIPE APRONEACH1$1,890.00$1,890.00$850.00$850.00$1,890.00$1,890.00$625.00$625.00$1,310.00$1,310.00$1,310.00$1,310.00$801.35$801.35
2501.51515" RC PIPE APRONEACH1$2,040.00$2,040.00$875.00$875.00$2,040.00$2,040.00$650.00$650.00$1,440.00$1,440.00$1,435.00$1,435.00$830.06$830.06
2502.502DRAINAGE SYSTEM TYPE (B910)LS1$5,000.00$5,000.00$4,000.00$4,000.00$3,500.00$3,500.00$1,050.00$1,050.00$1,800.00$1,800.00$2,000.00$2,000.00$1,980.00$1,980.00
2503.54112" RC PIPE SEWER DES 3006 CL VL F161$78.00$12,558.00$80.00$12,880.00$78.00$12,558.00$31.80$5,119.80$52.50$8,452.50$52.70$8,484.70$42.24$6,800.64
2503.54115" RC PIPE SEWER DES 3006 CL VL F161$80.00$12,880.00$80.00$12,880.00$80.00$12,880.00$34.30$5,522.30$52.50$8,452.50$52.70$8,484.70$41.69$6,712.09
2506.501CONST DRAINAGE STRUCTURE DES 48-4020L F17.7$1,180.00$20,886.00$405.00$7,168.50$1,180.00$20,886.00$293.00$5,186.10$360.00$6,372.00$360.00$6,372.00$387.86$6,865.12
2506.516CASTING ASSEMBLYEACH4$800.00$3,200.00$640.00$2,560.00$800.00$3,200.00$680.00$2,720.00$600.00$2,400.00$600.00$2,400.00$693.77$2,775.08
2506.602CONNECT INTO EXISTING DRAINAGE STRUCTUREEACH1$800.00$800.00$495.00$495.00$800.00$800.00$555.00$555.00$775.00$775.00$775.00$775.00$723.25$723.25
2511.501RANDOM RIPRAP CLASS IIC Y10$120.00$1,200.00$180.00$1,800.00$120.00$1,200.00$110.00$1,100.00$115.00$1,150.00$115.00$1,150.00$181.72$1,817.20
2514.501CONCRETE SLOPE PAVINGS Y446$70.00$31,220.00$110.00$49,060.00$125.00$55,750.00$114.00$50,844.00$115.00$51,290.00$175.00$78,050.00$137.50$61,325.00
2521.5014" CONCRETE WALKS F751$4.55$3,417.05$5.40$4,055.40$7.00$5,257.00$8.50$6,383.50$4.55$3,417.05$7.00$5,257.00$5.50$4,130.50
2531.501CONCRETE CURB & GUTTER DESIGN S512L F58$20.00$1,160.00$23.50$1,363.00$25.00$1,450.00$27.15$1,574.70$20.00$1,160.00$25.00$1,450.00$22.00$1,276.00
2531.501CONCRETE CURB & GUTTER DESIGN B618L F146$22.50$3,285.00$26.50$3,869.00$27.00$3,942.00$27.15$3,963.90$22.50$3,285.00$27.00$3,942.00$24.75$3,613.50
2531.501CONCRETE CURB & GUTTER DESIGN B418L F212$20.25$4,293.00$24.00$5,088.00$25.00$5,300.00$27.15$5,755.80$20.50$4,346.00$25.00$5,300.00$22.28$4,723.36
2531.5076" CONCRETE DRIVEWAY PAVEMENTS Y13$60.00$780.00$71.00$923.00$81.00$1,053.00$90.00$1,170.00$60.00$780.00$81.00$1,053.00$66.00$858.00
2531.618TRUNCATED DOMESS F16$38.50$616.00$45.50$728.00$37.00$592.00$53.00$848.00$38.50$616.00$37.00$592.00$42.35$677.60
2554.501TRAFFIC BARRIER DESIGN B8307L F112.5$17.40$1,957.50$20.50$2,306.25$17.40$1,957.50$18.60$2,092.50$17.50$1,968.75$17.40$1,957.50$26.13$2,939.63
2554.501TRAFFIC BARRIER DESIGN SPECIALL F100$50.30$5,030.00$58.50$5,850.00$50.30$5,030.00$53.70$5,370.00$50.50$5,050.00$50.30$5,030.00$65.73$6,573.00
2554.523END TREATMENT TANGENT TERMINALEACH2$2,090.00$4,180.00$2,440.00$4,880.00$2,090.00$4,180.00$2,231.00$4,462.00$2,090.00$4,180.00$2,090.00$4,180.00$2,750.00$5,500.00
2554.602GUARDRAIL CONNECTION SPECIALEACH2$75.00$150.00$87.50$175.00$75.00$150.00$80.00$160.00$75.00$150.00$75.00$150.00$110.00$220.00
2557.603TEMPORARY FENCE DESIGN SPECIALL F517$3.85$1,990.45$5.80$2,998.60$5.00$2,585.00$2.50$1,292.50$3.00$1,551.00$2.50$1,292.50$4.95$2,559.15
2557.603INSTALL CHAIN LINK FENCEL F21$50.00$1,050.00$29.00$609.00$50.00$1,050.00$32.00$672.00$10.00$210.00$20.00$420.00$55.00$1,155.00
2563.601TRAFFIC CONTROLLS1$17,884.00$17,884.00$27,000.00$27,000.00$20,000.00$20,000.00$19,050.00$19,050.00$17,900.00$17,900.00$18,000.00$18,000.00$42,625.00$42,625.00
2564.531SIGN PANELS TYPE SPECIALS F9$40.00$360.00$35.50$319.50$40.00$360.00$43.00$387.00$40.00$360.00$40.00$360.00$46.20$415.80
2564.531SIGN PANELS TYPE CS F19.5$40.00$780.00$63.00$1,228.50$40.00$780.00$43.00$838.50$40.00$780.00$40.00$780.00$41.25$804.38
2564.536INSTALL SIGN PANEL TYPE SPECIALEACH6$100.00$600.00$120.00$720.00$100.00$600.00$106.50$639.00$100.00$600.00$100.00$600.00$302.50$1,815.00
2564.536INSTALL SIGN PANEL TYPE CEACH8$100.00$800.00$120.00$960.00$100.00$800.00$106.50$852.00$100.00$800.00$100.00$800.00$137.50$1,100.00
2573.502SILT FENCE, TYPE MSL F218$2.75$599.50$3.40$741.20$4.00$872.00$2.00$436.00$2.50$545.00$2.50$545.00$4.40$959.20
2573.502SILT FENCE, TYPE HEAVY DUTYLIN FT102$3.00$306.00$5.70$581.40$3.90$397.80$2.20$224.40$3.90$397.80$3.90$397.80$6.60$673.20
2573.504SANDBAG BARRIERS F30$25.00$750.00$33.00$990.00$16.00$480.00$5.85$175.50$16.00$480.00$16.00$480.00$22.00$660.00
2573.530STORM DRAIN INLET PROTECTIONEACH1$500.00$500.00$295.00$295.00$165.00$165.00$112.00$112.00$165.00$165.00$165.00$165.00$357.50$357.50
2573.540FILTER LOG TYPE STRAW BIOROLLLIN FT100$3.50$350.00$4.90$490.00$3.90$390.00$3.35$335.00$3.90$390.00$3.90$390.00$3.30$330.00
2575.501SEEDINGACRE0.47$1,000.00$470.00$5,440.00$2,556.80$2,230.00$1,048.10$1,600.00$752.00$2,230.00$1,048.10$2,230.00$1,048.10$1,980.00$930.60
2575.502SEED MIXTURE 250POUND49$5.00$245.00$4.30$210.70$4.50$220.50$2.95$144.55$4.45$218.05$4.45$218.05$5.50$269.50
2575.505SODDING TYPE LAWNS Y102$6.50$663.00$17.00$1,734.00$18.40$1,876.80$5.30$540.60$18.50$1,887.00$18.40$1,876.80$5.23$533.46
2575.523EROSION CONTROL BLANKETS CATEGORY 2S Y1,122$1.30$1,458.60$1.70$1,907.40$1.70$1,907.40$1.25$1,402.50$1.65$1,851.30$1.65$1,851.30$1.82$2,042.04
2575.523EROSION CONTROL BLANKETS CATEGORY 3S Y1,139$1.40$1,594.60$2.60$2,961.40$1.50$1,708.50$1.25$1,423.75$1.50$1,708.50$1.50$1,708.50$2.37$2,699.43
2575.532FERTILIZER TYPE 3POUND165$1.00$165.00$1.50$247.50$0.90$148.50$0.60$99.00$0.90$148.50$0.90$148.50$1.10$181.50
2575.571RAPID STABILIZATION METHOD 3MGAL2$400.00$800.00$480.00$960.00$530.00$1,060.00$525.00$1,050.00$530.00$1,060.00$530.00$1,060.00$550.00$1,100.00
2575.601EROSION CONTROLLS1$2,500.00$2,500.00$5,790.00$5,790.00$5,800.00$5,800.00$7,000.00$7,000.00$5,200.00$5,200.00$5,240.00$5,240.00$3,850.00$3,850.00
2582.501PAVT MSSG (RT ARROW) EPOXYEACH2$145.00$290.00$240.00$480.00$145.00$290.00$154.50$309.00$145.00$290.00$145.00$290.00$143.00$286.00
2582.501PAVT MSSG (LT ARROW) EPOXYEACH2$145.00$290.00$240.00$480.00$145.00$290.00$154.50$309.00$145.00$290.00$145.00$290.00$143.00$286.00
2582.50212" SOLID LINE YELLOW-EPOXYL F64$8.00$512.00$9.20$588.80$8.00$512.00$8.50$544.00$8.00$512.00$8.00$512.00$5.50$352.00
2582.5024" DOUBLE SOLID LINE YELLOW-EPOXYL F669$1.56$1,043.64$3.70$2,475.30$1.60$1,070.40$1.65$1,103.85$1.56$1,043.64$1.56$1,043.64$2.22$1,485.18
2582.5024" SOLID LINE WHITE-EPOXYL F1,163$0.78$907.14$1.90$2,209.70$0.80$930.40$0.85$988.55$0.78$907.14$0.78$907.14$1.10$1,279.30
2582.503CROSSWALK MARKING-EPOXYS F198$8.00$1,584.00$8.10$1,603.80$8.00$1,584.00$8.50$1,683.00$8.00$1,584.00$8.00$1,584.00$4.84$958.32
 Totals for project 2121000 $1,470,307.25 $1,492,940.65 $1,499,812.50 $1,513,093.55 $1,556,632.23 $1,582,092.54 $1,929,864.26
 
Contract Total:$1,470,307.25$1,492,940.65$1,499,812.50$1,513,093.55$1,556,632.23$1,582,092.54$1,929,864.26