Hennepin County

Welcome, Guest!
Log in | Employee Login | License
 

Bid Abstract

2060600 - Replace Bridge 90480 over the West Arm Channel in OronoLunda Construction Company Edward Kraemer & Sons, Inc. 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal Price
2011.601VIBRATION MONITORINGLUMP SUM1$24,500.00$24,500.00$25,000.00$25,000.00
2021.501MOBILIZATIONLUMP SUM1$81,300.00$81,300.00$113,500.00$113,500.00
2031.501FIELD OFFICE TYPE DEACH1$25,200.00$25,200.00$20,000.00$20,000.00
2101.511CLEARING AND GRUBBINGLUMP SUM1$2,500.00$2,500.00$5,000.00$5,000.00
2104.501REMOVE GUARD RAIL-PLATE BEAMLIN FT295$3.00$885.00$3.50$1,032.50
2104.501REMOVE METAL CULVERTLIN FT94$9.00$846.00$9.00$846.00
2104.505REMOVE BITUMINOUS PAVEMENTSQ YD1,196$2.40$2,870.40$2.40$2,870.40
2104.513SAWING BIT PAVEMENT (FULL DEPTH)LIN FT214$4.00$856.00$4.00$856.00
2104.601REMOVE REGULATED WASTE MATERIAL (BRIDGE)LUMP SUM1$10,000.00$10,000.00$8,400.00$8,400.00
2105.501COMMON EXCAVATIONCU YD316$20.54$6,490.64$20.54$6,490.64
2105.507SUBGRADE EXCAVATIONCU YD389$20.54$7,990.06$20.54$7,990.06
2105.522SELECT GRANULAR BORROW MOD 10% (CV) (P)CU YD371$37.68$13,979.28$39.68$14,721.28
2105.543STABILIZING AGGREGATETON100$20.80$2,080.00$20.80$2,080.00
2105.609GRANULAR BORROWTON300$16.80$5,040.00$16.80$5,040.00
2105.609HAUL & DISPOSE OF CONTAMINATED MATERIALTON600$28.18$16,908.00$28.20$16,920.00
2118.501AGGREGATE SURFACING CLASS 2TON19$22.00$418.00$22.00$418.00
2123.610STREET SWEEPER (WITH PICKUP BROOM)HOUR8$125.00$1,000.00$150.00$1,200.00
2130.501WATERM GALLONS5$50.00$250.00$50.00$250.00
2131.502CALCIUM CHLORIDE SOLUTIONGALLON266$1.00$266.00$1.00$266.00
2211.501AGGREGATE BASE CLASS 5TON390$20.80$8,112.00$20.80$8,112.00
2301.553BRIDGE APPROACH PANELS (P)SQ YD230$100.00$23,000.00$150.00$34,500.00
2357.502BITUMINOUS MATERIAL FOR TACK COATGALLON102$3.00$306.00$3.00$306.00
2360.501TYPE SP 12.5 WEARING COURSE MIX (2,C)TON242$105.00$25,410.00$105.00$25,410.00
2360.502TYPE SP 12.5 NON WEAR COURSE MIX (2,B)TON162$105.00$17,010.00$105.00$17,010.00
2401.501STRUCTURAL CONCRETE (3Y43) (P)CU YD153$720.00$110,160.00$980.00$149,940.00
2401.501STRUCTURAL CONCRETE (1A43) (P)CU YD145$720.00$104,400.00$535.00$77,575.00
2401.512BRIDGE SLAB CONCRETE (3Y33HP) (P)SQ FT5,228$26.00$135,928.00$50.00$261,400.00
2401.513TYPE F (TL-4) RAILING CONCRETE (3Y46) (P)LIN FT372$125.00$46,500.00$100.00$37,200.00
2401.521STRUCTURE EXCAVATION CLASS E (P)CU YD733$18.90$13,853.70$20.00$14,660.00
2401.541REINFORCEMENT BARS (EPOXY COATED) (P)POUND69,271$1.25$86,588.75$1.18$81,739.78
2401.541REINFORCEMENT BARS (P)POUND11,452$1.10$12,597.20$1.09$12,482.68
2401.618BRIDGE DECK PLANING (P)SQ FT6,311$1.00$6,311.00$0.80$5,048.80
2402.583ORNAMENTAL METAL RAILING (P)LIN FT368$100.00$36,800.00$100.00$36,800.00
2402.590ELASTOMERIC BEARING PAD TYPE 1 (P)EACH14$500.00$7,000.00$500.00$7,000.00
2402.591EXPANSION JOINT DEVICES TYPE 2 (P)LIN FT89$200.00$17,800.00$200.00$17,800.00
2411.618ARCH SURFACE FINISH (MULTI COLOR) (P)SQ FT1,315$3.75$4,931.25$3.75$4,931.25
2411.618ARCHITECTURAL CONCRETE TEXTURE (ASHLAR STONE) (P)SQ FT1,315$35.00$46,025.00$13.00$17,095.00
2411.618SPECIAL SURFACE FINISH (P)SQ FT3,403$1.50$5,104.50$2.00$6,806.00
2442.501REMOVE EXISTING BRIDGELUMP SUM1$221,800.00$221,800.00$98,000.00$98,000.00
2452.507C-I-P CONCRETE PILING DELIVERED 12"LIN FT2,665$35.00$93,275.00$38.00$101,270.00
2452.507C-I-P CONCRETE PILING DELIVERED 16"LIN FT700$45.00$31,500.00$73.00$51,100.00
2452.508C-I-P CONCRETE PILING DRIVEN 16"LIN FT700$1.00$700.00$1.50$1,050.00
2452.508C-I-P CONCRETE PILING DRIVEN 12"LIN FT2,665$1.00$2,665.00$1.00$2,665.00
2452.519C-I-P CONC TEST PILE 80 FT LONG 12"EACH1$6,000.00$6,000.00$6,500.00$6,500.00
2452.519C-I-P CONC TEST PILE 80 FT LONG 16"EACH2$7,000.00$14,000.00$8,000.00$16,000.00
2452.519C-I-P CONC TEST PILE 55 FT LONG 12"EACH1$4,500.00$4,500.00$5,500.00$5,500.00
2452.519C-I-P CONC TEST PILE 65 FT LONG 12"EACH2$5,000.00$10,000.00$6,000.00$12,000.00
2452.519C-I-P CONC TEST PILE 90 FT LONG 12"EACH1$6,500.00$6,500.00$7,000.00$7,000.00
2452.602PILE ANALYSISEACH7$1,750.00$12,250.00$2,600.00$18,200.00
2501.51518" RC PIPE APRONEACH1$1,180.00$1,180.00$1,180.00$1,180.00
2501.602CONNECT TO INPLACE CULVERTEACH1$1,060.00$1,060.00$1,060.00$1,060.00
2501.602CONNECT TO INPLACE CULVERT SPECIALEACH1$920.00$920.00$920.00$920.00
2502.502DRAINAGE SYSTEM TYPE (B910)LUMP SUM1$2,500.00$2,500.00$5,000.00$5,000.00
2503.51115" CS PIPE SEWERLIN FT10$55.00$550.00$55.00$550.00
2503.51110" PVC PIPE SEWERLIN FT20$75.00$1,500.00$75.00$1,500.00
2503.54118" RC PIPE SEWER DES 3006LIN FT34$69.00$2,346.00$69.00$2,346.00
2503.54112" RC PIPE SEWER DES 3006LIN FT30$64.00$1,920.00$64.00$1,920.00
2503.601SANITARY SEWER SYSTEM MODIFICATIONLUMP SUM1$152,800.00$152,800.00$175,000.00$175,000.00
2503.602CONNECT INTO EXISTING DRAINAGE STRUCTUREEACH1$840.00$840.00$840.00$840.00
2506.501CONST DRAINAGE STRUCTURE DESIGN GLIN FT7.3$360.00$2,628.00$360.00$2,628.00
2506.501CONST DRAINAGE STRUCTURE DESIGN A OR FLIN FT22.6$280.00$6,328.00$280.00$6,328.00
2506.516CASTING ASSEMBLYEACH6$940.00$5,640.00$940.00$5,640.00
2506.522ADJUST FRAME & RING CASTINGEACH1$560.00$560.00$560.00$560.00
2506.603RECONSTRUCT SANITARY MANHOLESLIN FT6.2$290.00$1,798.00$290.00$1,798.00
2511.501RANDOM RIPRAP CLASS IIICU YD247$70.00$17,290.00$85.00$20,995.00
2511.501RANDOM RIPRAP CLASS IVCU YD244$70.00$17,080.00$85.00$20,740.00
2511.515GEOTEXTILE FILTER TYPE IV (MOD)SQ YD723$10.00$7,230.00$3.00$2,169.00
2531.501CONCRETE CURB & GUTTER DESIGN SPECIALLIN FT14$40.00$560.00$65.00$910.00
2531.501CONCRETE CURB & GUTTER DESIGN B624LIN FT92$32.00$2,944.00$40.00$3,680.00
2531.501CONCRETE CURB & GUTTER DESIGN B424LIN FT41$31.50$1,291.50$50.00$2,050.00
2533.507PORTABLE PRECAST CONC BARRIER DES 8337LIN FT125$14.50$1,812.50$14.50$1,812.50
2540.602RELOCATE MAIL BOX SUPPORTEACH3$150.00$450.00$150.00$450.00
2545.509CONDUIT SYSTEMLUMP SUM1$9,000.00$9,000.00$9,800.00$9,800.00
2554.501TRAFFIC BARRIER DESIGN B8307LIN FT25$23.00$575.00$23.15$578.75
2554.501TRAFFIC BARRIER DESIGN SPECIAL ALIN FT13$26.00$338.00$37.75$490.75
2554.501TRAFFIC BARRIER DESIGN SPECIALLIN FT75$54.00$4,050.00$49.55$3,716.25
2554.521ANCHORAGE ASSEMBLY-PLATE BEAMEACH1$350.00$350.00$565.00$565.00
2554.523END TREATMENT-ENERGY ABSORBING TERMINALEACH2$2,200.00$4,400.00$2,290.00$4,580.00
2563.601DETOUR SIGNINGLUMP SUM1$9,450.00$9,450.00$10,000.00$10,000.00
2563.601FLAGGING SPECIALLUMP SUM1$10,000.00$10,000.00$15,000.00$15,000.00
2563.601TRAFFIC CONTROLLUMP SUM1$5,000.00$5,000.00$27,000.00$27,000.00
2563.613PORTABLE CHANGEABLE MESSAGE SIGNUNIT DAY100$1.00$100.00$1.00$100.00
2563.613REFLECTORIZED DRUMUNIT DAY100$0.10$10.00$0.10$10.00
2563.6134'X4' SIGN WITH SUPPORTSUNIT DAY100$2.50$250.00$2.50$250.00
2563.613TYPE III BARRICADESUNIT DAY100$2.50$250.00$2.50$250.00
2563.613FLASHER TYPE B (HIGH INTENSITY)UNIT DAY100$0.10$10.00$0.10$10.00
2563.618CONSTRUCTION SIGN-SPECIALSQ FT100$10.00$1,000.00$10.00$1,000.00
2572.501TEMPORARY FENCELIN FT250$2.00$500.00$2.00$500.00
2573.502SILT FENCE, TYPE SUPER DUTYLIN FT50$50.00$2,500.00$32.00$1,600.00
2573.502SILT FENCE, TYPE HEAVY DUTYLIN FT918$2.00$1,836.00$2.00$1,836.00
2573.505FLOTATION SILT CURTAIN TYPE STILL WATERLIN FT306$10.50$3,213.00$10.50$3,213.00
2573.512TEMPORARY DITCH CHECK TYPE 3LIN FT48$4.00$192.00$4.00$192.00
2573.513TEMPORARY DITCH CHECK TYPE 7CU YD7$250.00$1,750.00$125.00$875.00
2573.520SEDIMENT REMOVAL BACKHOEHOUR10$200.00$2,000.00$300.00$3,000.00
2573.530STORM DRAIN INLET PROTECTIONEACH7$250.00$1,750.00$500.00$3,500.00
2573.550EROSION CONTROL SUPERVISORLUMP SUM1$30,000.00$30,000.00$5,000.00$5,000.00
2573.602TEMPORARY SEDIMENT TRAPEACH5$2,500.00$12,500.00$500.00$2,500.00
2575.502SEED MIXTURE 328POUND4$6.00$24.00$6.00$24.00
2575.505SODDING TYPE SALT RESISTANTSQ YD1,212$3.00$3,636.00$3.00$3,636.00
2575.523EROSION CONTROL BLANKETS CATEGORY 7SQ YD208$6.50$1,352.00$6.50$1,352.00
2575.532COMMERICAL FERTILIZER ANALYSIS 22-5-10POUND44$1.00$44.00$1.00$44.00
2575.607SELECT TOPSOIL BORROW (CV)CU YD175$24.00$4,200.00$24.00$4,200.00
 Totals for project 2060600 $1,655,914.78 $1,732,881.64
 
Contract Total:$1,655,914.78$1,732,881.64